A and B working together can complete the work in 12 days. A can complete the work in 20 days. If B does work for half day each day, then in what time can the work be completed.
The correct Answer is:15 days
To solve the problem, we need to determine how much work A and B can do together and how B's half-day work affects the total time taken to complete the work.
1. Determine the work done by A and B together:
- A and B together can complete the work in 12 days.
- Therefore, the work done by A and B together in one day is:
Work rate of A and B together=112 (work/day)
2. Determine the work done by A alone:
- A can complete the work in 20 days.
- Therefore, the work done by A in one day is:
Work rate of A=120 (work/day)
3. Determine the work done by B alone:
- Let the work done by B in one day be b.
- Since A and B together can complete the work in 12 days, we have:
120+b=112
- To find b, we solve the equation:
b=112−120
- Finding a common denominator (60):
b=560−360=260=130 (work/day)
- Thus, B can complete the work in 30 days.
4. Determine the effective work done by B when he works for half a day:
- If B works for half a day, the work done by B in half a day is:
Work done by B in half a day=12×130=160 (work)
5. Determine the total work done in one day when A works full day and B works half day:
- In one day, A works for a full day and B works for half a day, so the total work done in one day is:
Total work done in one day=120+160
- Finding a common denominator (60):
Total work done in one day=360+160=460=115 (work/day)
6. Calculate the total time to complete the work:
- Since the total work is 1 unit, the time taken to complete the work is:
Time=1 (total work)115 (work/day)=15 days
Final Answer:
The work can be completed in 15 days.
- A and B together can complete the work in 12 days.
- Therefore, the work done by A and B together in one day is:
Work rate of A and B together=112 (work/day)
- A can complete the work in 20 days.
- Therefore, the work done by A in one day is:
Work rate of A=120 (work/day)
- Let the work done by B in one day be b.
- Since A and B together can complete the work in 12 days, we have:
120+b=112
- To find b, we solve the equation:
b=112−120
- Finding a common denominator (60):
b=560−360=260=130 (work/day)
- Thus, B can complete the work in 30 days.
- If B works for half a day, the work done by B in half a day is:
Work done by B in half a day=12×130=160 (work)
- In one day, A works for a full day and B works for half a day, so the total work done in one day is:
Total work done in one day=120+160
- Finding a common denominator (60):
Total work done in one day=360+160=460=115 (work/day)
- Since the total work is 1 unit, the time taken to complete the work is:
Time=1 (total work)115 (work/day)=15 days
The work can be completed in 15 days.
Topper's Solved these Questions
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution
Knowledge Check
A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
A10 daysB20 daysC11 daysD15 daysA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
A10 daysB11 daysC15 daysD20 daysA can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?
A9B12C25D27
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
View SolutionA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
View Solution