(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?
The correct Answer is:4 days
To solve the problem step by step, we will first determine the work efficiencies of A, B, and C, and then calculate how much work is left after each phase of the work.
Step 1: Determine the total work
Since A + B can complete the job in 8 days, we can express the total work in terms of work units. If we assume the total work is 24 units (which is a common multiple of 8 and 12), then:
- Total work = 24 units
Step 2: Determine the efficiency of A + B
The efficiency of A + B can be calculated as follows:
- Efficiency of A + B = Total work / Time taken = 24 units / 8 days = 3 units/day
Step 3: Determine the efficiency of B and C
Since B and C together can complete the job in 12 days, we can calculate their combined efficiency:
- Efficiency of B + C = Total work / Time taken = 24 units / 12 days = 2 units/day
Step 4: Determine the efficiency of B
Now, we know that A + B's efficiency is 3 units/day and B + C's efficiency is 2 units/day. We can express A's efficiency as follows:
Let the efficiency of A be a, the efficiency of B be b, and the efficiency of C be c.
From the equations:
1. a+b=3 (1)
2. b+c=2 (2)
Step 5: Calculate the work done by A and B in the first 4 days
A and B work together for 4 days:
- Work done by A + B in 4 days = 4 days * 3 units/day = 12 units
Step 6: Calculate the remaining work
After A and B have worked for 4 days, the remaining work is:
- Remaining work = Total work - Work done = 24 units - 12 units = 12 units
Step 7: Calculate the work done by B in the next 2 days
B continues to work alone for 2 more days:
- Work done by B in 2 days = 2 days * b units/day
From equation (1), we can express b:
- Since a+b=3, we can substitute b=3−a.
Now, we need to find b using equation (2):
- From b+c=2, we can express c as c=2−b.
Step 8: Substitute and solve for B's efficiency
Assuming b=1 (since b+c=2 and it should be less than 2), we can find c:
- If b=1, then c=2−1=1.
Step 9: Work done by B in 2 days
Now, substituting b=1:
- Work done by B in 2 days = 2 days * 1 unit/day = 2 units
Step 10: Calculate the remaining work after B's contribution
After B works for 2 days, the remaining work is:
- Remaining work = 12 units - 2 units = 10 units
Step 11: Calculate how long C will take to finish the remaining work
C now starts working to finish the remaining 10 units of work. Since C's efficiency is 1 unit/day:
- Days required by C = Remaining work / C's efficiency = 10 units / 1 unit/day = 10 days
Final Answer
C will require 10 days to finish the job.
---
Since A + B can complete the job in 8 days, we can express the total work in terms of work units. If we assume the total work is 24 units (which is a common multiple of 8 and 12), then:
The efficiency of A + B can be calculated as follows:
Since B and C together can complete the job in 12 days, we can calculate their combined efficiency:
Now, we know that A + B's efficiency is 3 units/day and B + C's efficiency is 2 units/day. We can express A's efficiency as follows:
1. a+b=3 (1)
2. b+c=2 (2)
A and B work together for 4 days:
After A and B have worked for 4 days, the remaining work is:
B continues to work alone for 2 more days:
- Since a+b=3, we can substitute b=3−a.
- From b+c=2, we can express c as c=2−b.
Assuming b=1 (since b+c=2 and it should be less than 2), we can find c:
Now, substituting b=1:
After B works for 2 days, the remaining work is:
C now starts working to finish the remaining 10 units of work. Since C's efficiency is 1 unit/day:
C will require 10 days to finish the job.
Topper's Solved these Questions
Similar Questions
P and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution
Knowledge Check
A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?
A5B8C3D4A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 daysA and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in
A12 daysB14 daysC16 daysD24 days
A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
View SolutionA and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
View SolutionA and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
View Solution