(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:4 days


To solve the problem step by step, we will first determine the work efficiencies of A, B, and C, and then calculate how much work is left after each phase of the work.

Step 1: Determine the total work
Since A + B can complete the job in 8 days, we can express the total work in terms of work units. If we assume the total work is 24 units (which is a common multiple of 8 and 12), then:

- Total work = 24 units

Step 2: Determine the efficiency of A + B
The efficiency of A + B can be calculated as follows:

- Efficiency of A + B = Total work / Time taken = 24 units / 8 days = 3 units/day

Step 3: Determine the efficiency of B and C
Since B and C together can complete the job in 12 days, we can calculate their combined efficiency:

- Efficiency of B + C = Total work / Time taken = 24 units / 12 days = 2 units/day

Step 4: Determine the efficiency of B
Now, we know that A + B's efficiency is 3 units/day and B + C's efficiency is 2 units/day. We can express A's efficiency as follows:

Let the efficiency of A be a, the efficiency of B be b, and the efficiency of C be c.

From the equations:
1. a+b=3 (1)
2. b+c=2 (2)

Step 5: Calculate the work done by A and B in the first 4 days
A and B work together for 4 days:

- Work done by A + B in 4 days = 4 days * 3 units/day = 12 units

Step 6: Calculate the remaining work
After A and B have worked for 4 days, the remaining work is:

- Remaining work = Total work - Work done = 24 units - 12 units = 12 units

Step 7: Calculate the work done by B in the next 2 days
B continues to work alone for 2 more days:

- Work done by B in 2 days = 2 days * b units/day

From equation (1), we can express b:
- Since a+b=3, we can substitute b=3a.

Now, we need to find b using equation (2):
- From b+c=2, we can express c as c=2b.

Step 8: Substitute and solve for B's efficiency
Assuming b=1 (since b+c=2 and it should be less than 2), we can find c:

- If b=1, then c=21=1.

Step 9: Work done by B in 2 days
Now, substituting b=1:

- Work done by B in 2 days = 2 days * 1 unit/day = 2 units

Step 10: Calculate the remaining work after B's contribution
After B works for 2 days, the remaining work is:

- Remaining work = 12 units - 2 units = 10 units

Step 11: Calculate how long C will take to finish the remaining work
C now starts working to finish the remaining 10 units of work. Since C's efficiency is 1 unit/day:

- Days required by C = Remaining work / C's efficiency = 10 units / 1 unit/day = 10 days

Final Answer
C will require 10 days to finish the job.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

    A5
    B8
    C3
    D4
  • A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days