A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?
The correct Answer is:2515 days
To solve the problem step by step, we will first calculate the work done by A, B, and C, and then determine how long it takes to complete the entire work.
Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 25 days, so A's work rate is 125 of the work per day.
- B can complete the work in 40 days, so B's work rate is 140 of the work per day.
- C can complete the work in 60 days, so C's work rate is 160 of the work per day.
Step 2: Find the combined work rate of A, B, and C.
To find the combined work rate, we add their individual work rates:
Combined work rate=125+140+160
To add these fractions, we need to find a common denominator. The LCM of 25, 40, and 60 is 600.
Calculating each work rate:
- 125=24600
- 140=15600
- 160=10600
Now, adding them together:
Combined work rate=24+15+10600=49600
Step 3: Calculate the work done in the first 5 days.
In 5 days, the amount of work done by A, B, and C together is:
Work done in 5 days=5×49600=245600
Step 4: Determine the remaining work.
The total work is considered as 1 (or 600 units). The remaining work after 5 days is:
Remaining work=1−245600=355600
Step 5: Determine when B leaves the work.
Let x be the total number of days taken to complete the work. B leaves 10 days before the work is completed, which means B works for x−10 days.
Step 6: Calculate the work done by B and C after A leaves.
After 5 days, A leaves, and B and C continue working. Their combined work rate is:
B's work rate+C's work rate=140+160
Finding a common denominator (LCM of 40 and 60 is 120):
- 140=3120
- 160=2120
Adding them together:
B + C work rate=3+2120=5120=124
Step 7: Calculate the work done by B and C.
Let y be the number of days B and C work together after A leaves. Thus:
y=x−5−10=x−15
The work done by B and C together is:
Work done by B and C=(x−15)×124
Step 8: Set up the equation for total work.
The total work done can be expressed as:
245600+(x−15)×124=1
Step 9: Solve for x.
Rearranging the equation:
(x−15)×124=1−245600
Calculating the right side:
1−245600=600−245600=355600
Thus:
(x−15)×124=355600
Multiplying both sides by 24:
x−15=355×24600
Calculating the right side:
355×24600=8520600=14.2
Thus:
x−15=14.2⟹x=29.2
Step 10: Finalize the total time taken.
Since we are looking for the total time taken, we round x to the nearest whole number:
Total time taken=29.2 days≈30 days
Final Answer:
The total time taken to complete the work is approximately 30 days.
- A can complete the work in 25 days, so A's work rate is 125 of the work per day.
- B can complete the work in 40 days, so B's work rate is 140 of the work per day.
- C can complete the work in 60 days, so C's work rate is 160 of the work per day.
To find the combined work rate, we add their individual work rates:
Combined work rate=125+140+160
- 125=24600
- 140=15600
- 160=10600
Combined work rate=24+15+10600=49600
In 5 days, the amount of work done by A, B, and C together is:
Work done in 5 days=5×49600=245600
The total work is considered as 1 (or 600 units). The remaining work after 5 days is:
Remaining work=1−245600=355600
Let x be the total number of days taken to complete the work. B leaves 10 days before the work is completed, which means B works for x−10 days.
After 5 days, A leaves, and B and C continue working. Their combined work rate is:
B's work rate+C's work rate=140+160
- 140=3120
- 160=2120
B + C work rate=3+2120=5120=124
Let y be the number of days B and C work together after A leaves. Thus:
y=x−5−10=x−15
The work done by B and C together is:
Work done by B and C=(x−15)×124
The total work done can be expressed as:
245600+(x−15)×124=1
Rearranging the equation:
(x−15)×124=1−245600
Calculating the right side:
1−245600=600−245600=355600
Thus:
(x−15)×124=355600
Multiplying both sides by 24:
x−15=355×24600
Calculating the right side:
355×24600=8520600=14.2
Thus:
x−15=14.2⟹x=29.2
Since we are looking for the total time taken, we round x to the nearest whole number:
Total time taken=29.2 days≈30 days
The total time taken to complete the work is approximately 30 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?
View SolutionA and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View Solution