(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with half of his efficiency, then work will be completed in 4 days. In how many days will A and B do this work alone ?
The correct Answer is:10 days, 10 days
To solve the problem step by step, we will first define the efficiencies of A and B, then use the information given to find out how long each person would take to complete the work alone.
Step 1: Define the efficiencies of A and B
Let the efficiency of A be A units of work per day and the efficiency of B be B units of work per day.
Step 2: Set up the equation based on the first condition
According to the problem, A and B together can complete the work in 5 days. Therefore, the total work can be expressed as:
Total Work=(A+B)×5
Step 3: Set up the equation based on the second condition
When A works with twice his efficiency and B works with half his efficiency, they complete the same work in 4 days. This can be expressed as:
Total Work=(2A+B2)×4
Step 4: Equate the two expressions for total work
Since both expressions represent the same total work, we can set them equal to each other:
(A+B)×5=(2A+B2)×4
Step 5: Simplify the equation
Expanding both sides gives:
5A+5B=8A+2B
Rearranging the equation leads to:
5B−2B=8A−5A
This simplifies to:
3B=3A
Thus, we find:
A=B
Step 6: Substitute A in terms of B
Let’s denote both A and B as K (since they are equal):
A=KandB=K
Step 7: Find the total work in terms of K
Substituting A and B back into the total work equation:
Total Work=(K+K)×5=10K
Step 8: Calculate the time taken by A and B alone
Now, substituting back into the equation for total work:
10K=(2K+K2)×4
Simplifying the right side:
10K=(2K+0.5K)×4=(2.5K)×4=10K
This confirms our calculations are consistent.
Step 9: Calculate the time taken by A and B alone
Since A and B both work at K units per day, the time taken by A alone to complete the work is:
Time taken by A=Total WorkA=10KK=10 days
Similarly, the time taken by B alone is:
Time taken by B=Total WorkB=10KK=10 days
Conclusion
Thus, A will take 10 days to complete the work alone, and B will also take 10 days to complete the work alone.
---
Let the efficiency of A be A units of work per day and the efficiency of B be B units of work per day.
According to the problem, A and B together can complete the work in 5 days. Therefore, the total work can be expressed as:
Total Work=(A+B)×5
When A works with twice his efficiency and B works with half his efficiency, they complete the same work in 4 days. This can be expressed as:
Total Work=(2A+B2)×4
Since both expressions represent the same total work, we can set them equal to each other:
(A+B)×5=(2A+B2)×4
Expanding both sides gives:
5A+5B=8A+2B
Rearranging the equation leads to:
5B−2B=8A−5A
This simplifies to:
3B=3A
Thus, we find:
A=B
Let’s denote both A and B as K (since they are equal):
A=KandB=K
Substituting A and B back into the total work equation:
Total Work=(K+K)×5=10K
Now, substituting back into the equation for total work:
10K=(2K+K2)×4
Simplifying the right side:
10K=(2K+0.5K)×4=(2.5K)×4=10K
This confirms our calculations are consistent.
Since A and B both work at K units per day, the time taken by A alone to complete the work is:
Time taken by A=Total WorkA=10KK=10 days
Similarly, the time taken by B alone is:
Time taken by B=Total WorkB=10KK=10 days
Thus, A will take 10 days to complete the work alone, and B will also take 10 days to complete the work alone.
Topper's Solved these Questions
Similar Questions
(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with 13 of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?
View SolutionA and B working together can finish certain piece of work in 10 days. If A works at 23 of his actual efficiency and B works at 53 of his actual efficiency, then work will be completed in 9 days. If A works at 12 of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished?
View Solution
Knowledge Check
- Question 1 - Select One
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View Solution(A + B) can do a piece of work in 14 days. A works 312 days and B works for 1112 days, then half of the work has been completed. In how many days will B do this work alone ?
View Solution(A + B) can do a piece of work in 10 days. A works 212 days and B works for 812 days, then half of the work has been completed. In how many days will B do this work alone ?
View SolutionA and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with 112 times of his efficiency, then in how many days working together work will be finished?
View SolutionA can do a piece of work in x days. If new joins B who is twice as efficient as A, then in How many days can both finish double the work.
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View Solution