A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?

A

659days

B

629days

C

6 days

D

549days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(b)


To solve the problem step by step, we will follow these steps:

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 10 days, so A's work in one day = 110 of the work.
- B can complete the work in 12 days, so B's work in one day = 112 of the work.
- C can complete the work in 15 days, so C's work in one day = 115 of the work.

Step 2: Convert the work done in one day into a common unit.
To make calculations easier, we can find a common denominator. The least common multiple of 10, 12, and 15 is 60. Therefore:
- A's work in one day = 6010=6 units.
- B's work in one day = 6012=5 units.
- C's work in one day = 6015=4 units.

Step 3: Calculate the total work done by A and C in 4 days.
- A and C together can do 6+4=10 units of work in one day.
- In 4 days, they will complete 10×4=40 units of work.

Step 4: Determine the remaining work after A and C have worked for 4 days.
- Total work = 60 units.
- Work done by A and C in 4 days = 40 units.
- Remaining work = 6040=20 units.

Step 5: Calculate the work done by B and C together.
- After 4 days, A leaves and B joins C.
- B and C together can do 5+4=9 units of work in one day.

Step 6: Calculate the number of days required to complete the remaining work.
- Remaining work = 20 units.
- Work done by B and C in one day = 9 units.
- Days required to finish the remaining work = 209 days.

Step 7: Calculate the total time taken to complete the work.
- Total time = 4 days (A and C working) + 209 days (B and C working).
- To combine these, we convert 4 days into a fraction: 4=369.
- Total time = 369+209=569 days.

Final Answer:
The total work was completed in 569 days, which is approximately 6.22 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can alone complete a work in 15, 25 and 30 days
    respectively. A and B started the work and after some days A
    is replaced by C. Now the work is completed in a further of
    6 4/11 days. How much of the total work did B did ?

    A411
    B415
    C512
    D511
  • A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95
  • A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

    A5
    B4
    C3
    D6