A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
659days
629days
6 days
549days
The correct Answer is:(b)
To solve the problem step by step, we will follow these steps:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 10 days, so A's work in one day = 110 of the work.
- B can complete the work in 12 days, so B's work in one day = 112 of the work.
- C can complete the work in 15 days, so C's work in one day = 115 of the work.
Step 2: Convert the work done in one day into a common unit.
To make calculations easier, we can find a common denominator. The least common multiple of 10, 12, and 15 is 60. Therefore:
- A's work in one day = 6010=6 units.
- B's work in one day = 6012=5 units.
- C's work in one day = 6015=4 units.
Step 3: Calculate the total work done by A and C in 4 days.
- A and C together can do 6+4=10 units of work in one day.
- In 4 days, they will complete 10×4=40 units of work.
Step 4: Determine the remaining work after A and C have worked for 4 days.
- Total work = 60 units.
- Work done by A and C in 4 days = 40 units.
- Remaining work = 60−40=20 units.
Step 5: Calculate the work done by B and C together.
- After 4 days, A leaves and B joins C.
- B and C together can do 5+4=9 units of work in one day.
Step 6: Calculate the number of days required to complete the remaining work.
- Remaining work = 20 units.
- Work done by B and C in one day = 9 units.
- Days required to finish the remaining work = 209 days.
Step 7: Calculate the total time taken to complete the work.
- Total time = 4 days (A and C working) + 209 days (B and C working).
- To combine these, we convert 4 days into a fraction: 4=369.
- Total time = 369+209=569 days.
Final Answer:
The total work was completed in 569 days, which is approximately 6.22 days.
---
- A can complete the work in 10 days, so A's work in one day = 110 of the work.
- B can complete the work in 12 days, so B's work in one day = 112 of the work.
- C can complete the work in 15 days, so C's work in one day = 115 of the work.
To make calculations easier, we can find a common denominator. The least common multiple of 10, 12, and 15 is 60. Therefore:
- A's work in one day = 6010=6 units.
- B's work in one day = 6012=5 units.
- C's work in one day = 6015=4 units.
- A and C together can do 6+4=10 units of work in one day.
- In 4 days, they will complete 10×4=40 units of work.
- Total work = 60 units.
- Work done by A and C in 4 days = 40 units.
- Remaining work = 60−40=20 units.
- After 4 days, A leaves and B joins C.
- B and C together can do 5+4=9 units of work in one day.
- Remaining work = 20 units.
- Work done by B and C in one day = 9 units.
- Days required to finish the remaining work = 209 days.
- Total time = 4 days (A and C working) + 209 days (B and C working).
- To combine these, we convert 4 days into a fraction: 4=369.
- Total time = 369+209=569 days.
The total work was completed in 569 days, which is approximately 6.22 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
View Solution
Knowledge Check
A, B and C can alone complete a work in 15, 25 and 30 days
respectively. A and B started the work and after some days A
is replaced by C. Now the work is completed in a further of
6 4/11 days. How much of the total work did B did ?A411B415C512D511A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
A5B4C3D6
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution