Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.
66(2/3)
33(1/3)
16(2/3)
14(2/7)
The correct Answer is:(a)
To solve the problem step by step, let's break down the information given and calculate accordingly.
Step 1: Understand the Work Done by A
A can complete the work in x days. Therefore, A's work rate (efficiency) is:
Efficiency of A=1x (work per day)
Step 2: Calculate Work Done by A in 22 and 29 Days
A works for 2229 days. We convert this to an improper fraction:
2229=2009 days
The work done by A in this time is:
Work done by A=Efficiency of A×Time=1x×2009=2009x
Step 3: Remaining Work
Since the total work is 1 (whole work), the remaining work after A's contribution is:
Remaining Work=1−2009x=9x−2009x
Step 4: Work Done by B
B can complete the work in 2x days, so B's efficiency is:
Efficiency of B=12x
Let t be the time taken by B to complete the remaining work. The work done by B can be expressed as:
Work done by B=Efficiency of B×t=12x×t
Setting this equal to the remaining work:
12x×t=9x−2009x
Step 5: Time Taken by C and D Together
It is given that B completes the remaining work in the same time as C and D together can complete the whole work. The efficiency ratio of C and D is 4:5. Let the efficiencies of C and D be 4y and 5y respectively. Thus, their combined efficiency is:
Efficiency of C and D=4y+5y=9y
The time taken by C and D to complete the whole work is:
Time taken by C and D=19y
Step 6: Work Done by C and D in Alternative Days
C and D work alternately starting from C and can complete the total work in 4412 days:
4412=892 days
In 4412 days, they complete the work, which means:
Total Work=Total Days×Combined Efficiency=892×9y=801y2
Setting this equal to 1 (total work):
801y2=1⟹y=2801
Step 7: Substitute Back to Find x
Now we can substitute y back into the equations. The efficiency of C and D becomes:
Efficiency of C=4y=8801,Efficiency of D=5y=10801
Now, we can find t using the equation from Step 4:
12x×t=9x−2009x
Since t=19y:
12x×19y=9x−2009x
Substituting y:
12x×80118=9x−2009x
Cross-multiplying and solving for x:
80136x=9x−2009x
Solving this will lead to:
x=60018=33.33 days (or 3313 days)
Final Answer
Thus, the unique time x for A to complete the work is:
3313 days
A can complete the work in x days. Therefore, A's work rate (efficiency) is:
Efficiency of A=1x (work per day)
A works for 2229 days. We convert this to an improper fraction:
2229=2009 days
The work done by A in this time is:
Work done by A=Efficiency of A×Time=1x×2009=2009x
Since the total work is 1 (whole work), the remaining work after A's contribution is:
Remaining Work=1−2009x=9x−2009x
B can complete the work in 2x days, so B's efficiency is:
Efficiency of B=12x
Let t be the time taken by B to complete the remaining work. The work done by B can be expressed as:
Work done by B=Efficiency of B×t=12x×t
Setting this equal to the remaining work:
12x×t=9x−2009x
It is given that B completes the remaining work in the same time as C and D together can complete the whole work. The efficiency ratio of C and D is 4:5. Let the efficiencies of C and D be 4y and 5y respectively. Thus, their combined efficiency is:
Efficiency of C and D=4y+5y=9y
The time taken by C and D to complete the whole work is:
Time taken by C and D=19y
C and D work alternately starting from C and can complete the total work in 4412 days:
4412=892 days
In 4412 days, they complete the work, which means:
Total Work=Total Days×Combined Efficiency=892×9y=801y2
Setting this equal to 1 (total work):
801y2=1⟹y=2801
Now we can substitute y back into the equations. The efficiency of C and D becomes:
Efficiency of C=4y=8801,Efficiency of D=5y=10801
Now, we can find t using the equation from Step 4:
12x×t=9x−2009x
Since t=19y:
12x×19y=9x−2009x
Substituting y:
12x×80118=9x−2009x
Cross-multiplying and solving for x:
80136x=9x−2009x
Solving this will lead to:
x=60018=33.33 days (or 3313 days)
Thus, the unique time x for A to complete the work is:
3313 days
Topper's Solved these Questions
Similar Questions
A can do a work in x days and B can do the same work in y days. If x>y , then who can do more work in 6 days?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View Solution
Knowledge Check
A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 daysA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 daysA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12
A can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionA can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
View SolutionA can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionA and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
View Solution