P can complete a task in 15 days Q is 50% more efficient
then P. Both P and Q started working together on the
task and after few day Q lift task and P finished the
remaining 1/3of the given work. For how many days P and Q worled together.
3
5
4
6
The correct Answer is:(c)
To solve the problem step by step, we will analyze the work done by P and Q and determine how many days they worked together.
Step 1: Determine the work rate of P
P can complete the task in 15 days. Therefore, the work rate of P is:
Work rate of P=115 (work per day)
Step 2: Determine the work rate of Q
Q is 50% more efficient than P. This means Q can do 1.5 times the work that P can do in a day. Thus, the work rate of Q is:
Work rate of Q=1.5×115=1.515=110 (work per day)
Step 3: Calculate the combined work rate of P and Q
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=115+110
To add these fractions, we need a common denominator, which is 30:
Combined work rate=230+330=530=16 (work per day)
Step 4: Determine the total work done
Since P finished the remaining 13 of the work alone, it means that together they completed 1−13=23 of the work.
Step 5: Calculate the time taken by P and Q to complete 23 of the work
Let x be the number of days P and Q worked together. The amount of work they completed together in x days is:
Work done together=x×16
Setting this equal to 23:
x×16=23
Step 6: Solve for x
To solve for x, we can multiply both sides by 6:
x=23×6=4
Conclusion
P and Q worked together for 4 days.
---
P can complete the task in 15 days. Therefore, the work rate of P is:
Work rate of P=115 (work per day)
Q is 50% more efficient than P. This means Q can do 1.5 times the work that P can do in a day. Thus, the work rate of Q is:
Work rate of Q=1.5×115=1.515=110 (work per day)
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=115+110
To add these fractions, we need a common denominator, which is 30:
Combined work rate=230+330=530=16 (work per day)
Since P finished the remaining 13 of the work alone, it means that together they completed 1−13=23 of the work.
Let x be the number of days P and Q worked together. The amount of work they completed together in x days is:
Work done together=x×16
Setting this equal to 23:
x×16=23
To solve for x, we can multiply both sides by 6:
x=23×6=4
P and Q worked together for 4 days.
Topper's Solved these Questions
Similar Questions
P can do a piece of work in 9 days. Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :
View SolutionRanjith can complete a task in 25 days while Anji can finish it in 20 days .They work together on the task for 5 days and then Ranjith leaves in how many days Anji finish the remaining work ?
View Solution
Knowledge Check
P can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?
A1312B412C6D3P can complete a work in 72 days. Q is 33.33% more efficient
than P. In how many days both complete the work if they
work on alternate days starting with P?A56 daysB60 daysC62 daysDnone of theseP can do a piece of work in 36 days. If Q is 50% more efficient than P, then in how many days can Q do the same work?
A18B24C12D21
P alone can do a work in 25 days. P is 40% less efficient than Q. In how many days can Q alone do the work?
View SolutionP alone can do a work in 60 days. P is 40% less efficient than Q. In how many days can Q alone do the same work?
View SolutionP alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View SolutionP can complete a work in 15 days.Q can complete the same work in 10 days ,P started working and after 5 days Q joined him. How many days more will they take to complete the remaining work ?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View Solution