X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
449
940
489
9
The correct Answer is:A
To solve the problem of how many days X and Y will take to complete the task together, we can follow these steps:
Step 1: Determine the work done by each person in one day.
- X can complete the task in 8 days. Therefore, the work done by X in one day is:
Work done by X in one day=18
- Y can complete the task in 10 days. Therefore, the work done by Y in one day is:
Work done by Y in one day=110
Step 2: Add the work done by both X and Y in one day.
- When X and Y work together, their combined work done in one day is:
Combined work=18+110
Step 3: Find a common denominator to add the fractions.
- The least common multiple (LCM) of 8 and 10 is 40. Thus, we can rewrite the fractions:
18=540and110=440
- Now, we can add them:
Combined work=540+440=940
Step 4: Calculate the total time taken to complete the task together.
- If X and Y together complete 940 of the task in one day, then the total number of days D to complete the entire task (1 unit of work) is given by:
D=1Combined work=1940=409
Step 5: Convert the result into a more understandable format.
- The result 409 can be expressed as:
409≈4.44 daysor449 days
Final Answer:
- Therefore, X and Y together will complete the task in 409 days or approximately 4 days and 4/9 of a day.
---
- X can complete the task in 8 days. Therefore, the work done by X in one day is:
Work done by X in one day=18
- Y can complete the task in 10 days. Therefore, the work done by Y in one day is:
Work done by Y in one day=110
- When X and Y work together, their combined work done in one day is:
Combined work=18+110
- The least common multiple (LCM) of 8 and 10 is 40. Thus, we can rewrite the fractions:
18=540and110=440
- Now, we can add them:
Combined work=540+440=940
- If X and Y together complete 940 of the task in one day, then the total number of days D to complete the entire task (1 unit of work) is given by:
D=1Combined work=1940=409
- The result 409 can be expressed as:
409≈4.44 daysor449 days
- Therefore, X and Y together will complete the task in 409 days or approximately 4 days and 4/9 of a day.
Similar Questions
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
A alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?
A221B17C421D121A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 daysA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionVirat can complete a task a 20 days, whereas Anu can complete the same task in 15 days. How long will it take for Virat and Anu to complete the task if they worked together
View SolutionWorking for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?
View SolutionRavi can complete a task in 6 days and Mohan can complete the same task in 9 days. In how many days can Ravi and Mohan together complete the same task?
View SolutionPersons A, B and C can complete a task together in 81 days. A and B can complete the same task together in 97.2 days. B and C can complete the same task together in 162 days. In how many days can B alone complete the task?
View Solution