Working for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?
12
8
10
9
The correct Answer is:B
To solve the problem step by step, we will first determine the total work done by each person (X, Y, and Z) in terms of a common unit and then find out how long it will take for them to complete the task together.
Step 1: Calculate the work done by each person
1. Work done by X:
- X can finish a task in 3 days working 9 hours a day.
- Total hours worked by X = 3 days × 9 hours/day = 27 hours.
- Therefore, the total work done by X = 1 task.
2. Work done by Y:
- Y can finish three times the same task in 8 days working 9 hours a day.
- Total hours worked by Y = 8 days × 9 hours/day = 72 hours.
- Since Y completes 3 tasks in that time, the work done by Y for 1 task = 72 hours / 3 = 24 hours.
3. Work done by Z:
- Z can finish five times the same task in 12 days working 9 hours a day.
- Total hours worked by Z = 12 days × 9 hours/day = 108 hours.
- Since Z completes 5 tasks in that time, the work done by Z for 1 task = 108 hours / 5 = 21.6 hours.
Step 2: Calculate the work rates of X, Y, and Z
- Work rate of X = 1 task / 27 hours = 1/27 tasks per hour.
- Work rate of Y = 1 task / 24 hours = 1/24 tasks per hour.
- Work rate of Z = 1 task / 21.6 hours = 1/21.6 tasks per hour.
Step 3: Combine their work rates
To find the combined work rate of X, Y, and Z:
Combined work rate=127+124+121.6
Step 4: Find a common denominator and add the fractions
The least common multiple (LCM) of 27, 24, and 21.6 can be calculated. However, for simplicity, we can convert these fractions to a common denominator:
1. Convert each fraction:
- 127=24×124×27=24648
- 124=27×127×24=27648
- 121.6=30×130×21.6=30648
Now, add them:
Combined work rate=24+27+30648=81648=18 tasks per hour
Step 5: Calculate the time taken to complete 1 task
If they work together at a rate of 18 tasks per hour, the time taken to complete 1 task is:
Time=1 task18 tasks/hour=8 hours
Conclusion
Thus, working together, X, Y, and Z will complete the task in 8 hours.
---
- X can finish a task in 3 days working 9 hours a day.
- Total hours worked by X = 3 days × 9 hours/day = 27 hours.
- Therefore, the total work done by X = 1 task.
- Y can finish three times the same task in 8 days working 9 hours a day.
- Total hours worked by Y = 8 days × 9 hours/day = 72 hours.
- Since Y completes 3 tasks in that time, the work done by Y for 1 task = 72 hours / 3 = 24 hours.
- Z can finish five times the same task in 12 days working 9 hours a day.
- Total hours worked by Z = 12 days × 9 hours/day = 108 hours.
- Since Z completes 5 tasks in that time, the work done by Z for 1 task = 108 hours / 5 = 21.6 hours.
- Work rate of Y = 1 task / 24 hours = 1/24 tasks per hour.
- Work rate of Z = 1 task / 21.6 hours = 1/21.6 tasks per hour.
Combined work rate=127+124+121.6
- 127=24×124×27=24648
- 124=27×127×24=27648
- 121.6=30×130×21.6=30648
Combined work rate=24+27+30648=81648=18 tasks per hour
Time=1 task18 tasks/hour=8 hours
Topper's Solved these Questions
- SSC SELECTION POST (6 NOV 2020) SHIFT 3 HSCBOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST (6 NOV 2020) SHIFT 3 HSCEXERCISE - SECTION : QUANTITATIVE APTITUDE
25 Videos
- SSC SELECTION POST 10 NOV 2020 SHIFT 1 MATRICULATION LEVELBOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST 10 NOV 2020 SHIFT 1 MATRICULATION LEVELEXERCISE - Section : Quantitative Aptitude
25 Videos
Similar Questions
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
A449B940C489D9A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
A5B18C25D20X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?
A45B50C60D30
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:
View SolutionRavi can complete a task in 6 days and Mohan can complete the same task in 9 days. In how many days can Ravi and Mohan together complete the same task?
View SolutionA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
View SolutionA can complete a work in 18 days, B can do the same work in half the time as A. What part of work can be completed by both of them working together in 1 day
View Solution