Working for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?

A

12

B

8

C

10

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the total work done by each person (X, Y, and Z) in terms of a common unit and then find out how long it will take for them to complete the task together.

Step 1: Calculate the work done by each person

1. Work done by X:
- X can finish a task in 3 days working 9 hours a day.
- Total hours worked by X = 3 days × 9 hours/day = 27 hours.
- Therefore, the total work done by X = 1 task.

2. Work done by Y:
- Y can finish three times the same task in 8 days working 9 hours a day.
- Total hours worked by Y = 8 days × 9 hours/day = 72 hours.
- Since Y completes 3 tasks in that time, the work done by Y for 1 task = 72 hours / 3 = 24 hours.

3. Work done by Z:
- Z can finish five times the same task in 12 days working 9 hours a day.
- Total hours worked by Z = 12 days × 9 hours/day = 108 hours.
- Since Z completes 5 tasks in that time, the work done by Z for 1 task = 108 hours / 5 = 21.6 hours.

Step 2: Calculate the work rates of X, Y, and Z

- Work rate of X = 1 task / 27 hours = 1/27 tasks per hour.
- Work rate of Y = 1 task / 24 hours = 1/24 tasks per hour.
- Work rate of Z = 1 task / 21.6 hours = 1/21.6 tasks per hour.

Step 3: Combine their work rates

To find the combined work rate of X, Y, and Z:
Combined work rate=127+124+121.6

Step 4: Find a common denominator and add the fractions

The least common multiple (LCM) of 27, 24, and 21.6 can be calculated. However, for simplicity, we can convert these fractions to a common denominator:

1. Convert each fraction:
- 127=24×124×27=24648
- 124=27×127×24=27648
- 121.6=30×130×21.6=30648

Now, add them:
Combined work rate=24+27+30648=81648=18 tasks per hour

Step 5: Calculate the time taken to complete 1 task

If they work together at a rate of 18 tasks per hour, the time taken to complete 1 task is:
Time=1 task18 tasks/hour=8 hours

Conclusion

Thus, working together, X, Y, and Z will complete the task in 8 hours.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?

    A449
    B940
    C489
    D9
  • A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?

    A5
    B18
    C25
    D20
  • X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?

    A45
    B50
    C60
    D30