A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many days will the work be completed ? 15 days b. 22 days c. 25 days d. 35 days
To solve the problem step by step, we will follow the process outlined in the video transcript.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 24 days, so A's work in one day = 124.
- B can complete the work in 36 days, so B's work in one day = 136.
- C can complete the work in 48 days, so C's work in one day = 148.
Step 2: Calculate the combined work done by A, B, and C in one day.
Work done by A, B, and C in one day=124+136+148
To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 36, and 48 is 144.
Converting each fraction:
- 124=6144
- 136=4144
- 148=3144
Now, adding them together:
6144+4144+3144=13144
Step 3: Calculate the work done in the first 4 days.
In 4 days, A, B, and C will complete:
Work done in 4 days=4×13144=52144=1336
Step 4: Calculate the remaining work after 4 days.
The total work is considered as 1 (or 1 whole unit). Therefore, the remaining work is:
Remaining work=1−1336=36−1336=2336
Step 5: Determine how much work is done by B alone in the last 3 days.
Since A leaves 3 days before the work is completed, only B works for the last 3 days. B's work in one day is 136, so in 3 days, B will complete:
Work done by B in 3 days=3×136=336=112
Step 6: Calculate the remaining work after B's contribution.
After B works for 3 days, the remaining work is:
Remaining work=2336−112
To subtract these fractions, we convert 112 to have a common denominator of 36:
112=336
Thus,
Remaining work=2336−336=2036=59
Step 7: Calculate the work done by A and B together.
A and B together can complete:
A's work+B's work=124+136
Finding a common denominator (which is 72):
- 124=372
- 136=272
Thus,
Work done by A and B together=372+272=572
Step 8: Calculate the time taken by A and B to complete the remaining work.
To find the time taken to complete 59 work at a rate of 572:
Time=Remaining workWork done per day=5/95/72=59×725=729=8 days
Step 9: Calculate the total time taken to complete the work.
The total time taken is:
Total time=Time with A, B, and C+Time with B+Time with A and B
=4+3+8=15 days
Final Answer
The work will be completed in 15 days.
---
- A can complete the work in 24 days, so A's work in one day = 124.
- B can complete the work in 36 days, so B's work in one day = 136.
- C can complete the work in 48 days, so C's work in one day = 148.
Work done by A, B, and C in one day=124+136+148
To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 36, and 48 is 144.
- 124=6144
- 136=4144
- 148=3144
6144+4144+3144=13144
In 4 days, A, B, and C will complete:
Work done in 4 days=4×13144=52144=1336
The total work is considered as 1 (or 1 whole unit). Therefore, the remaining work is:
Remaining work=1−1336=36−1336=2336
Since A leaves 3 days before the work is completed, only B works for the last 3 days. B's work in one day is 136, so in 3 days, B will complete:
Work done by B in 3 days=3×136=336=112
After B works for 3 days, the remaining work is:
Remaining work=2336−112
To subtract these fractions, we convert 112 to have a common denominator of 36:
112=336
Thus,
Remaining work=2336−336=2036=59
A and B together can complete:
A's work+B's work=124+136
Finding a common denominator (which is 72):
- 124=372
- 136=272
Work done by A and B together=372+272=572
To find the time taken to complete 59 work at a rate of 572:
Time=Remaining workWork done per day=5/95/72=59×725=729=8 days
The total time taken is:
Total time=Time with A, B, and C+Time with B+Time with A and B
=4+3+8=15 days
The work will be completed in 15 days.
Topper's Solved these Questions
Similar Questions
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
A20 daysB18 daysC16 daysD15 daysA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution