A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
1425 days
9days
8days
759 days
The correct Answer is:C
To solve the problem, we need to find out how many days A worked before leaving. Let's break down the solution step by step.
Step 1: Determine the work rates of A and B
- A can complete the work in 28 days, so A's work rate is 128 of the work per day.
- B can complete the work in 35 days, so B's work rate is 135 of the work per day.
Step 2: Calculate the combined work rate of A and B
When A and B work together, their combined work rate is:
Combined work rate=128+135
To add these fractions, we need a common denominator. The least common multiple of 28 and 35 is 140.
Converting the fractions:
128=5140and135=4140
Thus,
Combined work rate=5140+4140=9140
Step 3: Set up the equation for the work done
Let x be the number of days A worked before leaving. The work done by A and B together in x days is:
Work done by A and B in x days=x×9140
Step 4: Calculate the work done by B after A leaves
After A leaves, B works alone for 17 days. The work done by B in 17 days is:
Work done by B in 17 days=17×135=1735
Step 5: Total work equation
The total work is equal to 1 (the whole work). Therefore, we can set up the equation:
x×9140+1735=1
Step 6: Solve for x
First, convert 1735 to a fraction with a denominator of 140:
1735=68140
Now, substitute this back into the equation:
x×9140+68140=1
Multiply through by 140 to eliminate the denominator:
9x+68=140
Now, solve for x:
9x=140−68
9x=72
x=729=8
Conclusion
A worked for 8 days before leaving.
- A can complete the work in 28 days, so A's work rate is 128 of the work per day.
- B can complete the work in 35 days, so B's work rate is 135 of the work per day.
When A and B work together, their combined work rate is:
Combined work rate=128+135
128=5140and135=4140
Thus,
Combined work rate=5140+4140=9140
Let x be the number of days A worked before leaving. The work done by A and B together in x days is:
Work done by A and B in x days=x×9140
After A leaves, B works alone for 17 days. The work done by B in 17 days is:
Work done by B in 17 days=17×135=1735
The total work is equal to 1 (the whole work). Therefore, we can set up the equation:
x×9140+1735=1
First, convert 1735 to a fraction with a denominator of 140:
1735=68140
x×9140+68140=1
Multiply through by 140 to eliminate the denominator:
9x+68=140
Now, solve for x:
9x=140−68
9x=72
x=729=8
A worked for 8 days before leaving.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (b)
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 20
10 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 20
10 Videos
- SURDS BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SURDS EXERCISE - UNIT TEST -1
15 Videos
- TRIANGLES BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLES EXERCISE - Self Assessment Sheet
10 Videos
Similar Questions
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View Solution
Knowledge Check
A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
A1425 daysB9 daysC8 daysD359 daysA and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 daysA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution