Doubtnut Promotions Sticky

8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

A

2012 days

B

2035 days

C

21days

D

2047 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine how many days it will take for 7 men working 10 hours a day to complete the same piece of work that 8 men can complete in 20 days working 9 hours a day.

1. Calculate the Total Work Done:
- The total work done can be calculated in terms of man-hours.
- If 8 men work for 9 hours a day for 20 days, the total work (in man-hours) is:
Total Work=Number of Men×Hours per Day×Number of Days
Total Work=8 men×9 hours/day×20 days=1440 man-hours

2. Calculate the Daily Work Done by 7 Men:
- Now, we need to calculate how much work 7 men can do in one day working 10 hours.
- The work done by 7 men in one day is:
Daily Work=7 men×10 hours/day=70 man-hours/day

3. Calculate the Number of Days Required:
- To find the number of days required for 7 men to complete the total work of 1440 man-hours, we divide the total work by the daily work:
Number of Days=Total WorkDaily Work=1440 man-hours70 man-hours/day=20.57 days
- Since we typically round up to the nearest whole number when dealing with days, we can say it will take approximately 21 days.

Final Answer:
7 men working for 10 hours a day can complete the same piece of work in approximately 21 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?

    A30 days
    B20 days
    C60 days
    D40 days
  • Question 2 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15 5/21 days
    B11 2/3 days
    C6 9/16 days
    D4 1/5 days
  • Question 3 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15521 days
    B1123 days
    C6916 days
    D415 days