If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

A

15521 days

B

1123 days

C

6916 days

D

415 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will use the concept of man-hours, which is the total amount of work done by a certain number of men in a certain number of hours.

Step 1: Calculate the total work done in man-hours by the first group of workers.

Given:
- Number of men = 20
- Hours worked per day = 7
- Days taken = 10

Total work (in man-hours) = Number of men × Hours per day × Days
Total work=20 men×7 hours/day×10 days=1400 man-hours

Step 2: Determine how many man-hours are needed for the second group of workers to complete the same work.

We already calculated that the total work required is 1400 man-hours.

Step 3: Calculate the number of days required for the second group of workers.

Given:
- Number of men = 15
- Hours worked per day = 8

Now, we need to find out how many days (let's denote it as d) it will take for 15 men working 8 hours a day to complete 1400 man-hours of work.

The total work done by 15 men in d days is:
Total work=15 men×8 hours/day×d days

Setting this equal to the total work required:
15×8×d=1400

Step 4: Solve for d.

120d=1400
d=1400120=35311.67 days

Thus, it will take approximately 11.67 days for 15 men working 8 hours a day to complete the same piece of work.

Final Answer:
15 men working 8 hours a day will complete the work in approximately 11.67 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15 5/21 days
    B11 2/3 days
    C6 9/16 days
    D4 1/5 days
  • 10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?

    AA)40 days
    BB)60 days
    CC)50 days
    DD)30 days
  • If 45 men can do a piece of work in 49 days, in how many days will 35 men do it?

    A63
    B53
    C43
    D33