A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

A

2

B

52

C

114

D

95

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 9 days, so A's work in one day = 19.
- B can complete the work in 12 days, so B's work in one day = 112.
- C can complete the work in 18 days, so C's work in one day = 118.

Step 2: Find the total work done by A, B, and C together in one day.
To find the total work done in one day, we add their individual work rates:
Total work in one day=19+112+118

To add these fractions, we need to find a common denominator. The LCM of 9, 12, and 18 is 36.
- Convert each fraction:
- 19=436
- 112=336
- 118=236

Now, adding them together:
Total work in one day=436+336+236=936=14

Step 3: Calculate the work done in the first 3 days.
Since they work together for 3 days, the total work done in 3 days is:
Work done in 3 days=3×14=34

Step 4: Determine the remaining work.
The total work is considered as 1 (or 100%). Therefore, the remaining work after 3 days is:
Remaining work=134=14

Step 5: Calculate the work done by B and C together.
Now, we need to find the combined work rate of B and C:
- B's work in one day = 112
- C's work in one day = 118

Finding a common denominator (which is 36):
- 112=336
- 118=236

Thus, the combined work of B and C in one day is:
Combined work of B and C=336+236=536

Step 6: Calculate the time taken by B and C to complete the remaining work.
To find out how many days it will take for B and C to complete the remaining 14 of the work:
Time=Remaining workCombined work of B and C=14536=14×365=3620=95 days

Final Answer:
The remaining work was completed in 95 days or 1.8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

    A203 days
    B253 days
    C6 days
    D5 days
  • A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11
  • A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

    A12
    B10
    C9.6
    D9