A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
2
52
114
95
The correct Answer is:D
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 9 days, so A's work in one day = 19.
- B can complete the work in 12 days, so B's work in one day = 112.
- C can complete the work in 18 days, so C's work in one day = 118.
Step 2: Find the total work done by A, B, and C together in one day.
To find the total work done in one day, we add their individual work rates:
Total work in one day=19+112+118
To add these fractions, we need to find a common denominator. The LCM of 9, 12, and 18 is 36.
- Convert each fraction:
- 19=436
- 112=336
- 118=236
Now, adding them together:
Total work in one day=436+336+236=936=14
Step 3: Calculate the work done in the first 3 days.
Since they work together for 3 days, the total work done in 3 days is:
Work done in 3 days=3×14=34
Step 4: Determine the remaining work.
The total work is considered as 1 (or 100%). Therefore, the remaining work after 3 days is:
Remaining work=1−34=14
Step 5: Calculate the work done by B and C together.
Now, we need to find the combined work rate of B and C:
- B's work in one day = 112
- C's work in one day = 118
Finding a common denominator (which is 36):
- 112=336
- 118=236
Thus, the combined work of B and C in one day is:
Combined work of B and C=336+236=536
Step 6: Calculate the time taken by B and C to complete the remaining work.
To find out how many days it will take for B and C to complete the remaining 14 of the work:
Time=Remaining workCombined work of B and C=14536=14×365=3620=95 days
Final Answer:
The remaining work was completed in 95 days or 1.8 days.
---
- A can complete the work in 9 days, so A's work in one day = 19.
- B can complete the work in 12 days, so B's work in one day = 112.
- C can complete the work in 18 days, so C's work in one day = 118.
To find the total work done in one day, we add their individual work rates:
Total work in one day=19+112+118
- Convert each fraction:
- 19=436
- 112=336
- 118=236
Total work in one day=436+336+236=936=14
Since they work together for 3 days, the total work done in 3 days is:
Work done in 3 days=3×14=34
The total work is considered as 1 (or 100%). Therefore, the remaining work after 3 days is:
Remaining work=1−34=14
Now, we need to find the combined work rate of B and C:
- B's work in one day = 112
- C's work in one day = 118
- 112=336
- 118=236
Combined work of B and C=336+236=536
To find out how many days it will take for B and C to complete the remaining 14 of the work:
Time=Remaining workCombined work of B and C=14536=14×365=3620=95 days
The remaining work was completed in 95 days or 1.8 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA, B and C can do a piece of work in 12, 15 and 20 days respectively. In how many days will all three do this work together ?
View Solution
Knowledge Check
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
A203 daysB253 daysC6 daysD5 daysA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
A12B10C9.6D9
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution