2 men or 5 women or 7 boys can finish a work in 469 days. then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :

A

134

B

106

C

100

D

98

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to determine how many days it will take for 7 men, 5 women, and 2 boys to finish the work, given that 2 men, 5 women, or 7 boys can finish the work in 469 days.

Step 1: Determine the work done by each group
Given:
- 2 men can finish the work in 469 days.
- 5 women can finish the work in 469 days.
- 7 boys can finish the work in 469 days.

This means:
- Work done by 2 men in 469 days = 1 work unit
- Work done by 5 women in 469 days = 1 work unit
- Work done by 7 boys in 469 days = 1 work unit

Step 2: Calculate the efficiency of each group
The efficiency (work done per day) can be calculated as:
- Efficiency of 2 men = 1469 work units per day
- Efficiency of 5 women = 1469 work units per day
- Efficiency of 7 boys = 1469 work units per day

Thus, the efficiency of each individual can be calculated as follows:
- Efficiency of 1 man = 12×1469=1938 work units per day
- Efficiency of 1 woman = 15×1469=12345 work units per day
- Efficiency of 1 boy = 17×1469=13283 work units per day

Step 3: Calculate the total efficiency of 7 men, 5 women, and 2 boys
Now, we calculate the total efficiency of 7 men, 5 women, and 2 boys:
- Total efficiency of 7 men = 7×1938=7938
- Total efficiency of 5 women = 5×12345=52345
- Total efficiency of 2 boys = 2×13283=23283

Step 4: Find a common denominator and add the efficiencies
To add these fractions, we need a common denominator. The least common multiple (LCM) of 938, 2345, and 3283 can be used.

After calculating the LCM, we can express each efficiency with that common denominator and sum them up.

Step 5: Calculate the total work done per day
Let’s denote the total efficiency as E. The total work done per day by 7 men, 5 women, and 2 boys will be E.

Step 6: Calculate the number of days to finish the work
The total number of days taken to finish the work can be calculated using the formula:
Days=1 work unitE

Final Calculation
After performing the calculations, we find that the total efficiency E leads to:
Days=98 days

Thus, the number of days taken by 7 men, 5 women, and 2 boys to finish the work is 98 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 8 men or 12 women can do a piece of work in 10 days, then what is the number of days required by 4 men and 4 women to finish the work ?

    A12 days
    B22 days
    C10 days
    DNone of these
  • If one man or two women or three boys can finish a work in 88 days, then how many days will one man, one woman and one boy together take to finish the same work?

    A46 days
    B54 days
    C48 days
    D44 days
  • If 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212

    A12.5
    B13
    C9.5
    D11