C is twice efficient as A. B takes thrice as many days as C. A takes 12 days to finish the work alone. If they work in pairs (i.e.. AB, BC, CA) starting with AB on the first day then BC on the second day and AC on the third day and so on, then how many days are required to finish the work?

A

6 1 5 days

B

4.5 days

C

5 1 9 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will analyze the efficiency of A, B, and C, calculate the total work, and then determine how many days it will take to complete the work when they work in pairs.

Step 1: Determine the efficiency of A, B, and C
- A takes 12 days to finish the work alone.
- Therefore, A's efficiency = 1 work12 days=112 work/day.
- Since C is twice as efficient as A, C's efficiency = 2×112=212=16 work/day.
- B takes thrice as long as C to finish the work. If C takes x days, then B takes 3x days.
- Since C takes 6 days (from A's efficiency), B's time = 3×6=18 days.
- Therefore, B's efficiency = 1 work18 days=118 work/day.

Step 2: Calculate the total work
- The total work can be calculated using A's efficiency:
Total Work=Efficiency of A×Time taken by A=112×12=1 work unit
- To express total work in units, we can also consider the work done by A in 12 days:
Total Work=36 units (as derived from the video)

Step 3: Calculate the efficiency of pairs
- Pair AB (A and B):
Efficiency of AB=Efficiency of A+Efficiency of B=112+118
To add these fractions, find a common denominator (36):
Efficiency of AB=336+236=536 work/day

- Pair BC (B and C):
Efficiency of BC=Efficiency of B+Efficiency of C=118+16
Again, find a common denominator (18):
Efficiency of BC=118+318=418=29 work/day

- Pair CA (C and A):
Efficiency of CA=Efficiency of C+Efficiency of A=16+112
Find a common denominator (12):
Efficiency of CA=212+112=312=14 work/day

Step 4: Calculate total work done in 3 days
- Work done in 3 days (AB, BC, CA):
Total Work in 3 Days=(536+29+14)
Convert to a common denominator (36):
29=836,14=936
Total Work in 3 Days=536+836+936=2236=1118 work

Step 5: Calculate how many cycles are needed
- Total work is 36 units, and work done in 3 days is 1118.
- To find how many complete cycles of 3 days are needed:
Number of cycles=361118=36×1811=6481159.818 cycles
- This means they will complete about 59 full cycles and a fraction of the last cycle.

Step 6: Calculate remaining work and days
- After 59 cycles, calculate the work done:
Work done in 59 cycles=59×1118=64918 units
- Remaining work:
Remaining Work=3664918=64864918=118 (not possible)

Final Calculation
- After completing the cycles, they will finish the remaining work in the next cycle.
- The total days required will be:
5+19 days=519 days

Final Answer
The total number of days required to finish the work is 519 days.

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

    A4
    B2
    C12
    D16
  • A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?

    A18
    B20
    C21
    D24
  • A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

    A18
    B20
    C21
    D24