(x2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x10) days. Then in how many days can (x+10) men finish the work?

A

27 days

B

12 days

C

25 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these steps:

Step 1: Set up the equations based on the information given.
We know that (x2) men can do a piece of work in x days. Therefore, the total work (W) can be expressed as:
\( W = (x - 2) \times x \)

Step 2: Express the work done by (x+7) men in (x10) days.
According to the problem, (x+7) men can do 75% of the same work in (x10) days. Thus, the work done by (x+7) men can be expressed as:
\( W_{75\%} = (x + 7) \times (x - 10) \)
Since this is 75% of the total work, we can write:
\( W_{75\%} = 0.75 \times W = 0.75 \times (x - 2) \times x \)

Step 3: Set the two expressions for work equal to each other.
Now we can set the two expressions for work equal to each other:
\( (x + 7)(x - 10) = 0.75 \times (x - 2) \times x \)

Step 4: Expand both sides of the equation.
Expanding the left side:
\( (x + 7)(x - 10) = x^2 - 10x + 7x - 70 = x^2 - 3x - 70 \)

Expanding the right side:
\( 0.75 \times (x - 2) \times x = 0.75(x^2 - 2x) = 0.75x^2 - 1.5x \)

Step 5: Set the equation to zero.
Now we can set the equation:
\( x^2 - 3x - 70 = 0.75x^2 - 1.5x \)

Rearranging gives:
\( x^2 - 0.75x^2 - 3x + 1.5x - 70 = 0 \)
\( 0.25x^2 - 1.5x - 70 = 0 \)

Step 6: Multiply through by 4 to eliminate the decimal.
Multiplying the entire equation by 4:
\( x^2 - 6x - 280 = 0 \)

Step 7: Factor the quadratic equation.
We can factor the quadratic:
\( (x - 20)(x + 14) = 0 \)

Step 8: Solve for x.
Setting each factor to zero gives:
1. \( x - 20 = 0 \) → \( x = 20 \)
2. \( x + 14 = 0 \) → \( x = -14 \) (not valid since x must be positive)

Thus, \( x = 20 \).

Step 9: Find the number of men.
Now, we need to find the number of men when \( x + 10 \):
\( x + 10 = 20 + 10 = 30 \text{ men} \)

Step 10: Calculate the total work.
Using the total work formula:
\( W = (x - 2) \times x = (20 - 2) \times 20 = 18 \times 20 = 360 \text{ units} \)

Step 11: Calculate the number of days for 30 men to finish the work.
Using the formula for the time taken:
\( \text{Days} = \frac{\text{Total Work}}{\text{Number of Men}} = \frac{360}{30} = 12 \text{ days} \)

Final Answer:
Thus, (x+10) men can finish the work in 12 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days

    A10
    B12
    C15
    D18
  • If x men can do a piece of work in y days, in how many days will x men do the same work ?

    Axzy
    Bxyz
    Cyzx
    Dxyz
  • If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17