If x men can do a piece of work In x days, then the number of days in which y men can do the same work is

A

xy days

B

y 2 x days

C

x 2 y days

D

x 2 y days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how many days it will take for y men to complete the same piece of work that x men can complete in x days.

1. Understanding the Work Done by x Men:
- If x men can complete the work in x days, we can calculate the total work in terms of man-days.
- Total work = Number of men × Number of days = x×x=x2 man-days.

2. Determining the Work Done by y Men:
- Now, we need to find out how many days it will take for y men to complete the same amount of work (which is x2 man-days).
- Let d be the number of days required for y men to complete the work.

3. Setting Up the Equation:
- The total work done by y men in d days is given by:
Total work=Number of men×Number of days=y×d
- Since we know the total work is x2, we can set up the equation:
y×d=x2

4. Solving for d:
- To find d, we rearrange the equation:
d=x2y

5. Conclusion:
- Therefore, the number of days in which y men can do the same work is x2y.

Final Answer:
The number of days in which y men can do the same work is x2y.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17
  • Question 2 - Select One

    If 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :

    A15
    B30
    C20
    D35
  • Question 3 - Select One

    If m men can do a work in r days, then the number of days taken by (m+n) men to do it is :

    Am+nmn
    Bm+nmr
    Cmrm+n
    D(m+n)rmn