6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?
6
8
9
15
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by the children and men, and then find out how many days it will take for 5 men to complete the same work.
Step 1: Define the Work Rate of Men and Children
Let the time taken by one man to complete the work be t. Then, the time taken by one child to complete the work is 2t (since each child takes twice the time taken by a man).
The work done by one man in one day is 1t and the work done by one child in one day is 12t.
Step 2: Calculate the Total Work Done by 6 Children and 2 Men
Now, we have 6 children and 2 men working together. The total work done by them in one day can be calculated as follows:
- Work done by 6 children in one day:
6×12t=62t=3t
- Work done by 2 men in one day:
2×1t=2t
- Total work done by 6 children and 2 men in one day:
Total work=3t+2t=5t
Step 3: Calculate the Total Work in 6 Days
Since they complete the work in 6 days, the total work can be calculated as:
Total Work=Work done in one day×Number of days=5t×6=30t
Step 4: Find the Work Done by 5 Men
Now, we need to find out how many days it will take for 5 men to complete the same total work of 30t.
The work done by 5 men in one day is:
5×1t=5t
Step 5: Calculate the Number of Days for 5 Men to Complete the Work
Let d be the number of days required for 5 men to complete the work. The equation is:
Total Work=Work done by 5 men in one day×d
Substituting the values we have:
30t=5t×d
Step 6: Solve for d
To find d, we can simplify the equation:
d=305=6
Thus, it will take 5 men 6 days to finish the same work.
Summary of Steps:
1. Define work rates for men and children based on their time to complete the work.
2. Calculate the total work done by 6 children and 2 men in one day.
3. Calculate the total work done in 6 days.
4. Find the work done by 5 men in one day.
5. Set up the equation to find the number of days d for 5 men to complete the work.
6. Solve for d.
Let the time taken by one man to complete the work be t. Then, the time taken by one child to complete the work is 2t (since each child takes twice the time taken by a man).
Now, we have 6 children and 2 men working together. The total work done by them in one day can be calculated as follows:
6×12t=62t=3t
2×1t=2t
Total work=3t+2t=5t
Since they complete the work in 6 days, the total work can be calculated as:
Total Work=Work done in one day×Number of days=5t×6=30t
Now, we need to find out how many days it will take for 5 men to complete the same total work of 30t.
5×1t=5t
Let d be the number of days required for 5 men to complete the work. The equation is:
Total Work=Work done by 5 men in one day×d
Substituting the values we have:
30t=5t×d
To find d, we can simplify the equation:
d=305=6
1. Define work rates for men and children based on their time to complete the work.
2. Calculate the total work done by 6 children and 2 men in one day.
3. Calculate the total work done in 6 days.
4. Find the work done by 5 men in one day.
5. Set up the equation to find the number of days d for 5 men to complete the work.
6. Solve for d.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
Knowledge Check
8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?
A9 daysB18 daysC12 daysD15 days8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?
A8B15C9D1216 children and 24 men complete a certain workin 18days. If each child takes twice the time taken by a man to finish the work, in how many days will 24 men finish the same work?
A12 daysB24 daysC36 daysD48 days
30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
View SolutionSixteen men can finish a work in 8 days. Eight men and nine women working together can finish the same work in 10 days. In how many days will twenty women finish the same work?
View Solution2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?
View Solution2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?
View Solution10 men and 15 women finish a work in 6 days. One man alone finishes that work in 100 days. In how many days will a women finish the work ?
View Solution