20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?

A

20

B

12

C

18

D

40

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the concept of work done by a certain number of persons in a given number of days.

Step 1: Determine the total work
Given that 20 persons completed 13 of the work in 24 days, we can denote the total work as 1 unit. Therefore, the work done by 20 persons in 24 days is:
W1=13

Step 2: Calculate the total work done by one person in one day
The work done by 20 persons in 24 days can be expressed as:
Work done by 20 persons in 24 days=20×24=480 person-days
Since this is equal to 13 of the total work, we can find the total work in person-days:
Total work in person-days=480×3=1440 person-days

Step 3: Determine the remaining work
The remaining work, which is W2, is:
W2=113=23

Step 4: Set up the equation for the remaining work
Let x be the number of additional persons required. The total number of persons working to complete the remaining work will be 20+x. They need to complete 23 of the work in 12 days. The equation for work done can be set up as:
(20+x)×12=23×1440

Step 5: Calculate the right-hand side
Calculating the right-hand side:
23×1440=960 person-days

Step 6: Substitute and solve for x
Now substituting back into the equation:
(20+x)×12=960
Dividing both sides by 12:
20+x=96012=80
Now, solving for x:
x=8020=60

Conclusion
Thus, the number of additional persons required to finish the remaining work in the next 12 days is:
60

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?

    A20
    B12
    C18
    D40
  • 100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?

    A100
    B60
    C80
    D40
  • 40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24