A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

A

25

B

50

C

75

D

can't be determined

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only (1)/(5)th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

    A20
    B35
    C30
    D25
  • A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    A10%
    B1427%
    C20%
    Dcan’t be determined
  • A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    Aa. 10%
    Bb. 1427%
    Cc. 20%
    Dd. can't be determined