A B and C can do a job in 6 days 12 days and 15 days respectively. After 1/8 of the work is completed C leaves the job. Rest of the work is done by A and B together Time taken to finish the remaning work is: a 35/6 days b 21/4 days c 7/2 days d 15/3 days
Correct option c 7/2 days Explanation:
Related Solutions
A, B and C can do a job in 6 days, 12 days and 15 days respectively. After of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
View SolutionA, B and C can do a job in 6 days, 12 days and 15 days respectively. After of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
View SolutionA, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View Solution(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View SolutionA can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionA can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?
View SolutionIf A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
View SolutionA, B and C can finish a work in 12 days, 15 days and 20 days respectively. They start working together. If B leaves after 3 days and C leaves 3 days before the completion of the work, then in how many days will the work be finished?
View SolutionA and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :
View SolutionA, B and C together can do a piece of work in 32 days. They work for 24 days and after that C leaves. A and B together can do the remaining work in 28 days. 1 day work done by A is equal to 2 days work done by B. Then in how many days they together will finish the work?
View SolutionA , B तथा C किसी काम को क्रमश : 24 दिन 9 दिन तथा 12 दिनों में कर सकते है B और C साथ काम करना आरभ करते है लेकिन 3 दिन बाद वे काम छोड़ देता है शेष काम A कितने दिनों में पूरा करेगा ?
View SolutionA, B and C can complete a work in 12, 15 and 18 days respectively. A worked alone for 2 days and after that B and C together finished the work. For how many days did B and C work?
View SolutionA, B and C together can finish a work in 28 days. All three work for 18 days. After that B leaves. If A and C finish the remaining work in 25 days. The work done by A in 2 days is equal to the work done by C in 3 days then in how many days will A, B and C finish the work separately?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View Solution