A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
4.33
4.5
4.66
None
The correct Answer is:D
To solve the problem step by step, we will determine how much work A, B, and C can do individually and then collectively to find out the total time taken to finish the work.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 18 days. Therefore, the work done by A in one day is:
Work done by A in one day=118
- B can complete the work in 9 days. Therefore, the work done by B in one day is:
Work done by B in one day=19
- C can complete the work in 6 days. Therefore, the work done by C in one day is:
Work done by C in one day=16
Step 2: Calculate the work done by A and B together in 2 days.
- The combined work done by A and B in one day is:
Work done by A and B in one day=118+19
To add these fractions, we need a common denominator. The least common multiple of 18 and 9 is 18.
19=218
Thus,
Work done by A and B in one day=118+218=318=16
- In 2 days, the work done by A and B is:
Work done by A and B in 2 days=2×16=26=13
Step 3: Calculate the remaining work after 2 days.
- The total work is considered as 1 unit. After A and B have worked for 2 days, the remaining work is:
Remaining work=1−13=23
Step 4: Calculate the work done by A, B, and C together in one day.
- Now, we calculate the combined work done by A, B, and C in one day:
Work done by A, B, and C in one day=118+19+16
Again, we need a common denominator. The least common multiple of 18, 9, and 6 is 18.
19=218,16=318
Thus,
Work done by A, B, and C in one day=118+218+318=618=13
Step 5: Calculate the number of days required to finish the remaining work.
- The remaining work is 23. The number of days required by A, B, and C to finish this remaining work is:
Days required=Remaining workWork done by A, B, and C in one day=2313=2 days
Step 6: Calculate the total number of days taken to finish the work.
- The total number of days taken to finish the work is:
Total days=Days worked by A and B+Days worked by A, B, and C=2+2=4 days
Final Answer:
The total number of days taken to finish the work is 4 days.
---
Work done by A in one day=118
Work done by B in one day=19
Work done by C in one day=16
Work done by A and B in one day=118+19
To add these fractions, we need a common denominator. The least common multiple of 18 and 9 is 18.
19=218
Thus,
Work done by A and B in one day=118+218=318=16
Work done by A and B in 2 days=2×16=26=13
Remaining work=1−13=23
Work done by A, B, and C in one day=118+19+16
Again, we need a common denominator. The least common multiple of 18, 9, and 6 is 18.
19=218,16=318
Thus,
Work done by A, B, and C in one day=118+218+318=618=13
Days required=Remaining workWork done by A, B, and C in one day=2313=2 days
Total days=Days worked by A and B+Days worked by A, B, and C=2+2=4 days
The total number of days taken to finish the work is 4 days.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 13(b)
15 Videos
- SIMPLE INTEREST BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTEREST EXERCISE - Self Assessment Sheet
10 Videos
- TRIANGLESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLESEXERCISE - Self Assessment Sheet - 18
10 Videos
Similar Questions
A can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C to do the work together.
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View Solution
Knowledge Check
A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
A6 daysB7 daysC9 daysD8 daysA can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?
A11B9C8D6A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16
A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?
View SolutionA can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View Solution