A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?

A

4.33

B

4.5

C

4.66

D

None

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will determine how much work A, B, and C can do individually and then collectively to find out the total time taken to finish the work.

Step 1: Determine the work done by A, B, and C in one day.

- A can complete the work in 18 days. Therefore, the work done by A in one day is:
Work done by A in one day=118

- B can complete the work in 9 days. Therefore, the work done by B in one day is:
Work done by B in one day=19

- C can complete the work in 6 days. Therefore, the work done by C in one day is:
Work done by C in one day=16

Step 2: Calculate the work done by A and B together in 2 days.

- The combined work done by A and B in one day is:
Work done by A and B in one day=118+19
To add these fractions, we need a common denominator. The least common multiple of 18 and 9 is 18.
19=218
Thus,
Work done by A and B in one day=118+218=318=16

- In 2 days, the work done by A and B is:
Work done by A and B in 2 days=2×16=26=13

Step 3: Calculate the remaining work after 2 days.

- The total work is considered as 1 unit. After A and B have worked for 2 days, the remaining work is:
Remaining work=113=23

Step 4: Calculate the work done by A, B, and C together in one day.

- Now, we calculate the combined work done by A, B, and C in one day:
Work done by A, B, and C in one day=118+19+16
Again, we need a common denominator. The least common multiple of 18, 9, and 6 is 18.
19=218,16=318
Thus,
Work done by A, B, and C in one day=118+218+318=618=13

Step 5: Calculate the number of days required to finish the remaining work.

- The remaining work is 23. The number of days required by A, B, and C to finish this remaining work is:
Days required=Remaining workWork done by A, B, and C in one day=2313=2 days

Step 6: Calculate the total number of days taken to finish the work.

- The total number of days taken to finish the work is:
Total days=Days worked by A and B+Days worked by A, B, and C=2+2=4 days

Final Answer:
The total number of days taken to finish the work is 4 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.

    A6 days
    B7 days
    C9 days
    D8 days
  • A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?

    A11
    B9
    C8
    D6
  • A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16