A can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in 45th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?

A

8

B

6

C

3

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Determine the work rates of A and B
- A can complete the work in 12 days, so A's work rate is:
A's work rate=112 (work per day)
- B can complete the work in 8 days, so B's work rate is:
B's work rate=18 (work per day)

Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
A + B's work rate=112+18
- To add these fractions, find a common denominator (which is 24):
A + B's work rate=224+324=524

Step 3: Calculate the work done by A and B in 3 days
- In 3 days, A and B together will complete:
Work done by A and B in 3 days=3×524=1524=58

Step 4: Determine the remaining work
- The total work is considered as 1 (the whole job), so the remaining work after A and B worked for 3 days is:
Remaining work=158=38

Step 5: Determine the time taken by C to complete the remaining work
- C can do the work in 45 of the time required by both A and B. First, we need to find the time required by A and B together:
Time required by A and B together=1A + B's work rate=1524=245 days
- Therefore, C's time to complete the work is:
C's time=45×245=9625 days
- C's work rate is:
C's work rate=19625=2596 (work per day)

Step 6: Calculate the time taken by C to complete the remaining work
- To find out how many days C worked to complete the remaining 38 of the work:
Time taken by C=Remaining workC's work rate=382596=38×9625=288200=7250=3625 days
- Converting 3625 to a mixed number gives:
3625=11125 days

Final Answer
C worked for 1 complete day.

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days
  • A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

    A5 days
    B10 days
    C15 days
    D20 days
  • A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?

    A24 days
    B18 days
    C20 days
    D16 days