A can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in 45th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?
8
6
3
None of these
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Determine the work rates of A and B
- A can complete the work in 12 days, so A's work rate is:
A's work rate=112 (work per day)
- B can complete the work in 8 days, so B's work rate is:
B's work rate=18 (work per day)
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
A + B's work rate=112+18
- To add these fractions, find a common denominator (which is 24):
A + B's work rate=224+324=524
Step 3: Calculate the work done by A and B in 3 days
- In 3 days, A and B together will complete:
Work done by A and B in 3 days=3×524=1524=58
Step 4: Determine the remaining work
- The total work is considered as 1 (the whole job), so the remaining work after A and B worked for 3 days is:
Remaining work=1−58=38
Step 5: Determine the time taken by C to complete the remaining work
- C can do the work in 45 of the time required by both A and B. First, we need to find the time required by A and B together:
Time required by A and B together=1A + B's work rate=1524=245 days
- Therefore, C's time to complete the work is:
C's time=45×245=9625 days
- C's work rate is:
C's work rate=19625=2596 (work per day)
Step 6: Calculate the time taken by C to complete the remaining work
- To find out how many days C worked to complete the remaining 38 of the work:
Time taken by C=Remaining workC's work rate=382596=38×9625=288200=7250=3625 days
- Converting 3625 to a mixed number gives:
3625=11125 days
Final Answer
C worked for 1 complete day.
- A can complete the work in 12 days, so A's work rate is:
A's work rate=112 (work per day)
- B can complete the work in 8 days, so B's work rate is:
B's work rate=18 (work per day)
- The combined work rate of A and B is:
A + B's work rate=112+18
- To add these fractions, find a common denominator (which is 24):
A + B's work rate=224+324=524
- In 3 days, A and B together will complete:
Work done by A and B in 3 days=3×524=1524=58
- The total work is considered as 1 (the whole job), so the remaining work after A and B worked for 3 days is:
Remaining work=1−58=38
- C can do the work in 45 of the time required by both A and B. First, we need to find the time required by A and B together:
Time required by A and B together=1A + B's work rate=1524=245 days
- Therefore, C's time to complete the work is:
C's time=45×245=9625 days
- C's work rate is:
C's work rate=19625=2596 (work per day)
- To find out how many days C worked to complete the remaining 38 of the work:
Time taken by C=Remaining workC's work rate=382596=38×9625=288200=7250=3625 days
- Converting 3625 to a mixed number gives:
3625=11125 days
C worked for 1 complete day.
Topper's Solved these Questions
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View Solution
Knowledge Check
A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 daysA and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 daysA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 days
(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
View Solution