A piece of work was to be completed in 40 days a number of men employed upon it did only half the work in 24 days, 16 more men were then set on, and the work was completed in the specified time, how many men were employed at first ?

A

16 men

B

32 men

C

24 men

D

48 men

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Understand the Work Done
The total work is to be completed in 40 days. According to the problem, half of the work was completed in 24 days.

Hint: Identify the total work in terms of days and the fraction of work done.

Step 2: Calculate the Total Work
Let the total work be represented as W. Since half of the work is done in 24 days, we can say:
Work done in 24 days=W2

Step 3: Determine the Work Rate
Let the number of men employed initially be n. The work done by n men in 24 days can be expressed as:
n×24=W2
From this, we can derive the work done by one man in one day:
n=W48

Step 4: Calculate Remaining Work
Since half of the work is completed, the remaining work is also W2. This remaining work needs to be completed in the remaining days, which is:
4024=16 days

Step 5: Set Up the Equation for Remaining Work
After 24 days, 16 more men are added, making the total number of men:
n+16
The equation for the remaining work can be set up as:
(n+16)×16=W2

Step 6: Substitute n into the Equation
Now we substitute n from Step 3 into the equation:
(W48+16)×16=W2

Step 7: Simplify the Equation
Expanding the left side:
W×1648+16×16=W2
This simplifies to:
W3+256=W2

Step 8: Solve for W
To solve for W, we can first eliminate the fractions by multiplying through by 6 (the least common multiple of 3 and 2):
2W+1536=3W
Rearranging gives:
3W2W=1536
Thus:
W=1536

Step 9: Find the Initial Number of Men
Now that we have W, we can find n:
n=W48=153648=32

Conclusion
The number of men employed at first was 32.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A30
    B40
    C32
    D36
  • A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?

    A30
    B15
    C25
    D20