A piece of work was to be completed in 40 days a number of men employed upon it did only half the work in 24 days, 16 more men were then set on, and the work was completed in the specified time, how many men were employed at first ?
16 men
32 men
24 men
48 men
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Understand the Work Done
The total work is to be completed in 40 days. According to the problem, half of the work was completed in 24 days.
Hint: Identify the total work in terms of days and the fraction of work done.
Step 2: Calculate the Total Work
Let the total work be represented as W. Since half of the work is done in 24 days, we can say:
Work done in 24 days=W2
Step 3: Determine the Work Rate
Let the number of men employed initially be n. The work done by n men in 24 days can be expressed as:
n×24=W2
From this, we can derive the work done by one man in one day:
n=W48
Step 4: Calculate Remaining Work
Since half of the work is completed, the remaining work is also W2. This remaining work needs to be completed in the remaining days, which is:
40−24=16 days
Step 5: Set Up the Equation for Remaining Work
After 24 days, 16 more men are added, making the total number of men:
n+16
The equation for the remaining work can be set up as:
(n+16)×16=W2
Step 6: Substitute n into the Equation
Now we substitute n from Step 3 into the equation:
(W48+16)×16=W2
Step 7: Simplify the Equation
Expanding the left side:
W×1648+16×16=W2
This simplifies to:
W3+256=W2
Step 8: Solve for W
To solve for W, we can first eliminate the fractions by multiplying through by 6 (the least common multiple of 3 and 2):
2W+1536=3W
Rearranging gives:
3W−2W=1536
Thus:
W=1536
Step 9: Find the Initial Number of Men
Now that we have W, we can find n:
n=W48=153648=32
Conclusion
The number of men employed at first was 32.
---
The total work is to be completed in 40 days. According to the problem, half of the work was completed in 24 days.
Let the total work be represented as W. Since half of the work is done in 24 days, we can say:
Work done in 24 days=W2
Let the number of men employed initially be n. The work done by n men in 24 days can be expressed as:
n×24=W2
From this, we can derive the work done by one man in one day:
n=W48
Since half of the work is completed, the remaining work is also W2. This remaining work needs to be completed in the remaining days, which is:
40−24=16 days
After 24 days, 16 more men are added, making the total number of men:
n+16
The equation for the remaining work can be set up as:
(n+16)×16=W2
Now we substitute n from Step 3 into the equation:
(W48+16)×16=W2
Expanding the left side:
W×1648+16×16=W2
This simplifies to:
W3+256=W2
To solve for W, we can first eliminate the fractions by multiplying through by 6 (the least common multiple of 3 and 2):
2W+1536=3W
Rearranging gives:
3W−2W=1536
Thus:
W=1536
Now that we have W, we can find n:
n=W48=153648=32
The number of men employed at first was 32.
Topper's Solved these Questions
Similar Questions
24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View Solution
Knowledge Check
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 menA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
A30B15C25D20
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution