Doubtnut Promotions Sticky

Ramesh can finish a job in 20 days. He worked for 10 days alone and completed the remaining job working with Dinesh, in 2 days. How many days would both Dinesh and Ramesh together take to complete the entire job ?

A

4

B

5

C

10

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for Ramesh can finish a job in 20 days. He worked for 10 days alone and completed the remaining job working with Dinesh, in 2 days. How many days would both Dinesh and Ramesh together take to complete the entire job ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 1 - Select One

    Sunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?

    A8
    B12
    C16
    D20
  • Question 1 - Select One

    A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

    A403 days
    B203
    C103 days
    D253 days
  • Question 1 - Select One

    A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?

    A8 days
    B7 days
    C6 days
    DNone of these
  • Question 1 - Select One

    Mukesh and Dinesh together can complete a work in 120 days. Mukesh alone can complete the work in 150 days. In how many days can Dinesh alone complete the work?

    A650
    B720
    C450
    D600
  • Question 1 - Select One

    A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?

    A60
    B50
    C40
    D30
  • Question 1 - Select One

    Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works 1.5 times as fast as Sunil. The three together can complete the work in

    A712
    B1512
    C157
    DNone of these

Similar Questions