Mugdha and Mayuri, working together can complete a job at 18 days. However, Mayuri works alone and leaves after completing two fifths of the job and then Mugdha takes over in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?

A

72

B

30

C

25

D

45

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step-by-step, we will follow the reasoning laid out in the video transcript.

Step 1: Determine the combined work rate of Mugdha and Mayuri
Mugdha and Mayuri together can complete the job in 18 days. Therefore, their combined work rate is:
Work rate of Mugdha and Mayuri=118 (job per day)

Step 2: Define variables for individual work rates
Let:
- x = number of days Mayuri takes to complete the job alone
- y = number of days Mugdha takes to complete the job alone

Then, their individual work rates are:
Work rate of Mayuri=1xandWork rate of Mugdha=1y

Step 3: Set up the equation based on the combined work rate
From the combined work rate, we have:
1x+1y=118
This is our first equation.

Step 4: Analyze the work done by Mayuri and Mugdha
Mayuri works alone and completes 25 of the job. The remaining 35 of the job is completed by Mugdha in 39 days.

The work done by Mayuri in terms of her work rate is:
Work done by Mayuri=25(of the job)
The time taken by Mayuri to complete this work is:
Time taken by Mayuri=251x=2x5

Step 5: Set up the equation for the remaining work done by Mugdha
Mugdha completes the remaining 35 of the job in 39 days, so we have:
35=391y
This gives us the second equation:
35=39yy=3953=65

Step 6: Substitute y into the first equation to find x
Now we can substitute y=65 into the first equation:
1x+165=118
To solve for x, we rearrange:
1x=118165
Finding a common denominator (which is 1170):
118=651170,165=181170
Thus:
1x=65181170=471170x=11704724.89 days

Step 7: Conclusion about Mugdha's work rate
Since Mayuri works faster than Mugdha, and we have found y=65 days for Mugdha, we conclude that Mugdha alone would take 65 days to complete the job.

Final Answer
Mugdha alone would have taken 65 days to complete the job.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone

    A60
    B30
    C45
    D40
  • Ramesh can finish a job in 20 days. He worked for 10 days alone and completed the remaining job working with Dinesh, in 2 days. How many days would both Dinesh and Ramesh together take to complete the entire job ?

    A4
    B5
    C10
    D12
  • A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

    A50
    B30
    C40
    D60