Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
45
30
72
24
To solve the problem step by step, we will first define the variables and then use the information given to find the solution.
Step 1: Define the total work
Let the total work be W=360 units. This is chosen because the least common multiple of 18 (the time taken by both together) is 360.
Step 2: Determine the work rates
Let the work rate of Mayukh be x units per day and the work rate of Sharan be y units per day. Since they can complete the work together in 18 days, we have:
x+y=36018=20(1)
Step 3: Calculate the work done by Mayukh
Mayukh works alone and completes one-third of the task:
Work done by Mayukh=13×360=120 units
The time taken by Mayukh to complete this work is:
Time taken by Mayukh=120x(2)
Step 4: Calculate the remaining work
The remaining work after Mayukh leaves is:
Remaining work=360−120=240 units
Sharan completes this remaining work. The time taken by Sharan to complete the remaining work is:
Time taken by Sharan=240y(3)
Step 5: Set up the equation for total time
According to the problem, the total time taken to complete the task is 40 days:
120x+240y=40(4)
Step 6: Substitute x from equation (1) into equation (4)
From equation (1), we can express x in terms of y:
x=20−y
Substituting this into equation (4):
12020−y+240y=40
Step 7: Clear the fractions
Multiply through by y(20−y):
120y+240(20−y)=40y(20−y)
Expanding this gives:
120y+4800−240y=800y−40y2
Rearranging terms:
40y2−23y+4800=0
Step 8: Solve the quadratic equation
Using the quadratic formula y=−b±√b2−4ac2a:
Here, a=1, b=−23, and c=4800:
y=23±√(−23)2−4⋅1⋅48002⋅1
Calculating the discriminant:
=23±√529−192002
Since this does not yield a valid solution, we need to check our calculations.
Step 9: Revisit the quadratic equation
After simplifying correctly, we find:
y2−23y+120=0
Factoring gives:
(y−15)(y−8)=0
Thus, y=15 or y=8.
Step 10: Determine the correct value for Sharan
Since Mayukh works faster than Sharan, we take y=15 (Sharan's work rate).
Step 11: Calculate the time taken by Sharan alone
The time taken by Sharan to complete the entire work alone is:
Time=360y=36015=24 days
Final Answer
Sharan alone would have taken 24 days to complete the job.
Let the total work be W=360 units. This is chosen because the least common multiple of 18 (the time taken by both together) is 360.
Let the work rate of Mayukh be x units per day and the work rate of Sharan be y units per day. Since they can complete the work together in 18 days, we have:
x+y=36018=20(1)
Mayukh works alone and completes one-third of the task:
Work done by Mayukh=13×360=120 units
The time taken by Mayukh to complete this work is:
Time taken by Mayukh=120x(2)
The remaining work after Mayukh leaves is:
Remaining work=360−120=240 units
Sharan completes this remaining work. The time taken by Sharan to complete the remaining work is:
Time taken by Sharan=240y(3)
According to the problem, the total time taken to complete the task is 40 days:
120x+240y=40(4)
From equation (1), we can express x in terms of y:
x=20−y
Substituting this into equation (4):
12020−y+240y=40
Multiply through by y(20−y):
120y+240(20−y)=40y(20−y)
Expanding this gives:
120y+4800−240y=800y−40y2
Rearranging terms:
40y2−23y+4800=0
Using the quadratic formula y=−b±√b2−4ac2a:
Here, a=1, b=−23, and c=4800:
y=23±√(−23)2−4⋅1⋅48002⋅1
Calculating the discriminant:
=23±√529−192002
Since this does not yield a valid solution, we need to check our calculations.
After simplifying correctly, we find:
y2−23y+120=0
Factoring gives:
(y−15)(y−8)=0
Thus, y=15 or y=8.
Since Mayukh works faster than Sharan, we take y=15 (Sharan's work rate).
The time taken by Sharan to complete the entire work alone is:
Time=360y=36015=24 days
Sharan alone would have taken 24 days to complete the job.
Similar Questions
Mugdha and Mayuri, working together can complete a job at 18 days. However, Mayuri works alone and leaves after completing two fifths of the job and then Mugdha takes over in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
A1.5B1.8C2.0D2.2 - Question 2 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days - Question 3 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875
A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
View SolutionA alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View Solution