A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :

A

33319

B

19625

C

44419

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will first determine the work rates of A and B, then find out how long A would take to complete the task alone.

Step 1: Determine the combined work rate of A and B

A and B can complete the task together in 30 days. Therefore, their combined work rate is:
Work rate of A and B=130 (tasks per day)

Step 2: Calculate the work done by A and B in 11 days

In 11 days, A and B together would complete:
Work done in 11 days=11×130=1130 of the task

Step 3: Determine the remaining work after 11 days

The remaining work after A and B have worked together for 11 days is:
Remaining work=11130=301130=1930 of the task

Step 4: Calculate the work done by A alone in 28 days

A completes the remaining 1930 of the task in 28 days. Therefore, A's work rate can be calculated as:
Work rate of A=193028=19840 (tasks per day)

Step 5: Determine the work rate of B

Since we know the combined work rate of A and B is 130, we can find B's work rate:
Work rate of B=Work rate of A and BWork rate of A
Work rate of B=13019840
To perform this subtraction, we need a common denominator. The least common multiple of 30 and 840 is 840.
130=28840
Now, substituting:
Work rate of B=2884019840=9840=193.33 (tasks per day)

Step 6: Calculate the number of days A would take to complete the task alone

To find out how long A would take to complete the entire task alone, we use A's work rate:
Days taken by A alone=1 task19840 tasks per day=8401944.21 days

Thus, the number of days taken by A to complete the task alone is approximately 44.21 days.

Final Answer:
A would take approximately 44.21 days to complete the task alone.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :

    A47311
    B4219
    C53711
    D44419
  • If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days
  • If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days