A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :
33319
19625
44419
none of these
The correct Answer is:C
To solve the problem, we will first determine the work rates of A and B, then find out how long A would take to complete the task alone.
Step 1: Determine the combined work rate of A and B
A and B can complete the task together in 30 days. Therefore, their combined work rate is:
Work rate of A and B=130 (tasks per day)
Step 2: Calculate the work done by A and B in 11 days
In 11 days, A and B together would complete:
Work done in 11 days=11×130=1130 of the task
Step 3: Determine the remaining work after 11 days
The remaining work after A and B have worked together for 11 days is:
Remaining work=1−1130=30−1130=1930 of the task
Step 4: Calculate the work done by A alone in 28 days
A completes the remaining 1930 of the task in 28 days. Therefore, A's work rate can be calculated as:
Work rate of A=193028=19840 (tasks per day)
Step 5: Determine the work rate of B
Since we know the combined work rate of A and B is 130, we can find B's work rate:
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=130−19840
To perform this subtraction, we need a common denominator. The least common multiple of 30 and 840 is 840.
130=28840
Now, substituting:
Work rate of B=28840−19840=9840=193.33 (tasks per day)
Step 6: Calculate the number of days A would take to complete the task alone
To find out how long A would take to complete the entire task alone, we use A's work rate:
Days taken by A alone=1 task19840 tasks per day=84019≈44.21 days
Thus, the number of days taken by A to complete the task alone is approximately 44.21 days.
Final Answer:
A would take approximately 44.21 days to complete the task alone.
---
Work rate of A and B=130 (tasks per day)
Work done in 11 days=11×130=1130 of the task
Remaining work=1−1130=30−1130=1930 of the task
Work rate of A=193028=19840 (tasks per day)
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=130−19840
To perform this subtraction, we need a common denominator. The least common multiple of 30 and 840 is 840.
130=28840
Now, substituting:
Work rate of B=28840−19840=9840=193.33 (tasks per day)
Days taken by A alone=1 task19840 tasks per day=84019≈44.21 days
A would take approximately 44.21 days to complete the task alone.
Topper's Solved these Questions
Similar Questions
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :
A47311B4219C53711D44419If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 daysIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days
A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?
View SolutionA alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?
View SolutionWorking together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
View SolutionA and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View Solution