The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:
4.5
5
6
913
The correct Answer is:C
To solve the problem step by step, we will first analyze the given information and then calculate the required values.
Step 1: Understand the Ratios of Efficiencies
The ratio of efficiencies of A to C is given as 5:3. This means:
- Efficiency of A = 5x
- Efficiency of C = 3x
Step 2: Understand the Days Taken by B and C
The ratio of the number of days taken by B to C is given as 2:3. Let the number of days taken by B be 2y and by C be 3y.
Step 3: Relate Days Taken by A and C
It is given that A takes 6 days less than C. Therefore, we can write:
- Days taken by A = Days taken by C - 6
- Days taken by A = 3y - 6
Step 4: Set Up the Equation for A's Days
Since we know A's efficiency is 5x and the time taken by A is (3y - 6), we can express the total work done as:
- Total Work = Efficiency × Time
- Total Work = 5x × (3y - 6)
Step 5: Calculate Total Work Using C's Days
For C, the total work can also be expressed as:
- Total Work = Efficiency × Time
- Total Work = 3x × 3y = 9xy
Step 6: Equate the Total Work Expressions
From the above expressions, we have:
5x(3y−6)=9xy
Step 7: Simplify the Equation
Expanding the left side:
15xy−30x=9xy
Now, rearranging gives:
15xy−9xy=30x
6xy=30x
Step 8: Solve for y
Dividing both sides by x (assuming x ≠ 0):
6y=30
y=5
Step 9: Calculate Days Taken by A, B, and C
Now we can find the number of days taken by each:
- Days taken by C = 3y = 3(5) = 15 days
- Days taken by B = 2y = 2(5) = 10 days
- Days taken by A = 3y - 6 = 15 - 6 = 9 days
Step 10: Calculate Total Work
Total work can be calculated using C's days:
- Total Work = 3x × 15 = 45x
Step 11: Calculate Work Done by B and C in 3 Days
Now, B and C worked together for 3 days:
- Work done by B in 3 days = Efficiency of B × Days = (3/2) × 3 = 4.5 units
- Work done by C in 3 days = Efficiency of C × Days = (3) × 3 = 9 units
- Total work done by B and C in 3 days = 4.5 + 9 = 13.5 units
Step 12: Calculate Remaining Work
Remaining work after 3 days:
- Remaining Work = Total Work - Work Done = 45 - 13.5 = 31.5 units
Step 13: Calculate Days Taken by A to Finish Remaining Work
Now, A will complete the remaining work:
- A's efficiency = 5x = 5(3) = 15 units/day
- Days taken by A to finish remaining work = Remaining Work / A's Efficiency = 31.5 / 15 = 2.1 days
Final Answer
The number of days taken by A to finish the remaining work is 2.1 days.
The ratio of efficiencies of A to C is given as 5:3. This means:
- Efficiency of A = 5x
- Efficiency of C = 3x
The ratio of the number of days taken by B to C is given as 2:3. Let the number of days taken by B be 2y and by C be 3y.
It is given that A takes 6 days less than C. Therefore, we can write:
- Days taken by A = Days taken by C - 6
- Days taken by A = 3y - 6
Since we know A's efficiency is 5x and the time taken by A is (3y - 6), we can express the total work done as:
- Total Work = Efficiency × Time
- Total Work = 5x × (3y - 6)
For C, the total work can also be expressed as:
- Total Work = Efficiency × Time
- Total Work = 3x × 3y = 9xy
From the above expressions, we have:
5x(3y−6)=9xy
Expanding the left side:
15xy−30x=9xy
Now, rearranging gives:
15xy−9xy=30x
6xy=30x
Dividing both sides by x (assuming x ≠ 0):
6y=30
y=5
Now we can find the number of days taken by each:
- Days taken by C = 3y = 3(5) = 15 days
- Days taken by B = 2y = 2(5) = 10 days
- Days taken by A = 3y - 6 = 15 - 6 = 9 days
Total work can be calculated using C's days:
- Total Work = 3x × 15 = 45x
Now, B and C worked together for 3 days:
- Work done by B in 3 days = Efficiency of B × Days = (3/2) × 3 = 4.5 units
- Work done by C in 3 days = Efficiency of C × Days = (3) × 3 = 9 units
- Total work done by B and C in 3 days = 4.5 + 9 = 13.5 units
Remaining work after 3 days:
- Remaining Work = Total Work - Work Done = 45 - 13.5 = 31.5 units
Now, A will complete the remaining work:
- A's efficiency = 5x = 5(3) = 15 units/day
- Days taken by A to finish remaining work = Remaining Work / A's Efficiency = 31.5 / 15 = 2.1 days
The number of days taken by A to finish the remaining work is 2.1 days.
Topper's Solved these Questions
Similar Questions
The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View Solution
Knowledge Check
The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:
A4.5B5C6D913The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :
A4.5B5C6D913A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
A3B5C10D121
The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
View SolutionThe rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View Solution