The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:

A

4.5

B

5

C

6

D

913

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first analyze the given information and then calculate the required values.

Step 1: Understand the Ratios of Efficiencies
The ratio of efficiencies of A to C is given as 5:3. This means:
- Efficiency of A = 5x
- Efficiency of C = 3x

Step 2: Understand the Days Taken by B and C
The ratio of the number of days taken by B to C is given as 2:3. Let the number of days taken by B be 2y and by C be 3y.

Step 3: Relate Days Taken by A and C
It is given that A takes 6 days less than C. Therefore, we can write:
- Days taken by A = Days taken by C - 6
- Days taken by A = 3y - 6

Step 4: Set Up the Equation for A's Days
Since we know A's efficiency is 5x and the time taken by A is (3y - 6), we can express the total work done as:
- Total Work = Efficiency × Time
- Total Work = 5x × (3y - 6)

Step 5: Calculate Total Work Using C's Days
For C, the total work can also be expressed as:
- Total Work = Efficiency × Time
- Total Work = 3x × 3y = 9xy

Step 6: Equate the Total Work Expressions
From the above expressions, we have:
5x(3y6)=9xy

Step 7: Simplify the Equation
Expanding the left side:
15xy30x=9xy
Now, rearranging gives:
15xy9xy=30x
6xy=30x

Step 8: Solve for y
Dividing both sides by x (assuming x ≠ 0):
6y=30
y=5

Step 9: Calculate Days Taken by A, B, and C
Now we can find the number of days taken by each:
- Days taken by C = 3y = 3(5) = 15 days
- Days taken by B = 2y = 2(5) = 10 days
- Days taken by A = 3y - 6 = 15 - 6 = 9 days

Step 10: Calculate Total Work
Total work can be calculated using C's days:
- Total Work = 3x × 15 = 45x

Step 11: Calculate Work Done by B and C in 3 Days
Now, B and C worked together for 3 days:
- Work done by B in 3 days = Efficiency of B × Days = (3/2) × 3 = 4.5 units
- Work done by C in 3 days = Efficiency of C × Days = (3) × 3 = 9 units
- Total work done by B and C in 3 days = 4.5 + 9 = 13.5 units

Step 12: Calculate Remaining Work
Remaining work after 3 days:
- Remaining Work = Total Work - Work Done = 45 - 13.5 = 31.5 units

Step 13: Calculate Days Taken by A to Finish Remaining Work
Now, A will complete the remaining work:
- A's efficiency = 5x = 5(3) = 15 units/day
- Days taken by A to finish remaining work = Remaining Work / A's Efficiency = 31.5 / 15 = 2.1 days

Final Answer
The number of days taken by A to finish the remaining work is 2.1 days.

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:

    A4.5
    B5
    C6
    D913
  • The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :

    A4.5
    B5
    C6
    D913
  • A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is

    A3
    B5
    C10
    D121