The rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
2:3
4:9
3:2
9:4
The correct Answer is:C
To solve the problem, we need to find the ratio of the number of days taken by A and B to finish the work, given their rates of working.
1. Understand the Given Ratio of Efficiency:
The rates of working of A and B are in the ratio of 2:3. This means:
- Efficiency of A = 2 parts
- Efficiency of B = 3 parts
2. Define the Work Done:
Let's assume the total work to be done is a constant amount, say 1 unit of work.
3. Calculate the Time Taken by Each:
The time taken to complete the work is inversely proportional to the efficiency. Therefore:
- Time taken by A = Total Work / Efficiency of A = 1 / 2
- Time taken by B = Total Work / Efficiency of B = 1 / 3
4. Find the Ratio of Days Taken:
To find the ratio of the days taken by A and B, we take the reciprocal of their efficiencies:
- Ratio of days taken by A to B = (1/2) : (1/3)
5. Simplify the Ratio:
To simplify (1/2) : (1/3), we can multiply both sides by 6 (the least common multiple of the denominators):
- (1/2) * 6 : (1/3) * 6 = 3 : 2
6. Conclusion:
The ratio of the number of days taken by A and B to finish the work is 3:2.
Final Answer:
The number of days taken by A and B to finish the work is in the ratio 3:2.
---
The rates of working of A and B are in the ratio of 2:3. This means:
- Efficiency of A = 2 parts
- Efficiency of B = 3 parts
Let's assume the total work to be done is a constant amount, say 1 unit of work.
The time taken to complete the work is inversely proportional to the efficiency. Therefore:
- Time taken by A = Total Work / Efficiency of A = 1 / 2
- Time taken by B = Total Work / Efficiency of B = 1 / 3
To find the ratio of the days taken by A and B, we take the reciprocal of their efficiencies:
- Ratio of days taken by A to B = (1/2) : (1/3)
To simplify (1/2) : (1/3), we can multiply both sides by 6 (the least common multiple of the denominators):
- (1/2) * 6 : (1/3) * 6 = 3 : 2
The ratio of the number of days taken by A and B to finish the work is 3:2.
The number of days taken by A and B to finish the work is in the ratio 3:2.
Topper's Solved these Questions
- RATIO AND PROPORTION BOOK - KIRAN PUBLICATIONCHAPTER - RATIO AND PROPORTION EXERCISE - TEST YOURSELF
19 Videos
- RATIO AND PROPORTION BOOK - KIRAN PUBLICATIONCHAPTER - RATIO AND PROPORTION EXERCISE - TYPE-VIII
5 Videos
- PROFIT AND LOSS BOOK - KIRAN PUBLICATIONCHAPTER - PROFIT AND LOSS EXERCISE - TEST YOURSELF
23 Videos
- SEQUENCE AND SERIES BOOK - KIRAN PUBLICATIONCHAPTER - SEQUENCE AND SERIES EXERCISE - TEST YOURSELF
20 Videos
Similar Questions
Find the mean proportional between 100 and 625.
View SolutionThere Is a ratio of 5:4 between two numbers. If 40 per cent of the first Is 12, then 50% of the second number is
View SolutionThe selling price of 13 articles is same as the cost price of 23 articles. What is the profit percentage?
View SolutionIn the sequence of number 0, 7, 26, 63,…..215, 342 the missing term is
View Solutionएक कार्य को समाप्त करने के लिए P तथा Q की कार्यक्षमता का अनुपात 3:4 है तो काम को ख़त्म करने के लिए दोनों के द्वारा लिए गए दिनों का अनुपात क्या होगा ?
View Solutionएक कार्य को समाप्त करने के लिए p तथा Q की कार्यक्षमता का अनुपात 3 : 4 है तो काम को ख़त्म करने के लिए दोनों के द्वारा लिए गए दिनों का अनुपात क्या होगा ?
View Solutiona के 2 दिनों का काम b के 3 दिनों के काम के बराबर है यदि a काम को 8 दिनों में समाप्त का सकता है , तो b काम को कितने दिनों में समाप्त करेगा ?
View SolutionA और B के काम करने की दर २:३ के अनुपात में है उसके द्वारा काम को पूरा करने में लिए गए दिनों का अनुपात क्या होगा ?
View SolutionThe rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
View SolutionThe ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :
View SolutionThe ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:
View SolutionThe ratio of efficiency of A and B is 3 : 5 and that of B and C is 2 : 3 respectively. If A and B work for 4 days then remaining work is finished by C in 8 days. Then in how many days B alone will finish the work?
View SolutionA started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View SolutionA can finish 25 of work done by B in 14 of time taken by B. B can finish 43 of work done by C in 35 of time taken by C. Working together they can finish the work in 60 days. In how many days they will finish the work, working alone?
View SolutionThe ratio of the number of days required by A,B and C to do a piece of work hours is 1:2:3. Then, the ratio of work is ……………
View Solution