The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
A
3:4
B
9:16
C
4:3
D
None of these
Video Solution
Text Solution
The correct Answer is:C
|
Answer
Step by step video, text & image solution for The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Related Playlists
Knowledge Check
- Question 1 - Select One
The rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
A2:3B4:9C3:2D9:4 - Question 1 - Select One
Working efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio
A3:2B2:3C3:4D4:3 - Question 1 - Select One
The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?
A. 7:5
B. 3:4
C. 4:3
D. 5:7AABDCBDC - Question 1 - Select One
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
A9B18C15D12 - Question 1 - Select One
A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
A4B2C12D16 - Question 1 - Select One
The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :
A4.5B5C6D913 - Question 1 - Select One
The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:
A4.5B5C6D913 - Question 1 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days - Question 1 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days