A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?

A

16 days

B

18 days

C

20 days

D

22 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work in terms of units
A and B can complete the work together in 8 days. Therefore, their combined work rate is:
Work rate of A and B together=1 work8 days=18 work per day

Step 2: Determine B's work rate
B alone can complete the work in 12 days. Therefore, B's work rate is:
Work rate of B=1 work12 days=112 work per day

Step 3: Determine A's work rate
To find A's work rate, we can use the combined work rate:
Work rate of A=Work rate of A and BWork rate of B
Work rate of A=18112
To subtract these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
18=324,112=224
Work rate of A=324224=124 work per day

Step 4: Calculate the work done by A and B in 4 days
When A and B work together for 4 days, the amount of work they complete is:
Work done in 4 days=4×Work rate of A and B
Work done in 4 days=4×18=48=12 work

Step 5: Calculate the remaining work
Since the total work is 1, the remaining work after B leaves is:
Remaining work=112=12 work

Step 6: Calculate the time taken by A to complete the remaining work
Now, we need to find out how long it will take A to complete the remaining work:
Time taken by A=Remaining workWork rate of A
Time taken by A=12124=12×24=12 days

Conclusion
Thus, A will take 12 days to complete the remaining work after B leaves.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16
  • A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?

    A40
    B36
    C45
    D32
  • A and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?

    A15 days
    B18 days
    C16 days
    D20 days