A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?
16 days
18 days
20 days
22 days
The correct Answer is:A
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the total work in terms of units
A and B can complete the work together in 8 days. Therefore, their combined work rate is:
Work rate of A and B together=1 work8 days=18 work per day
Step 2: Determine B's work rate
B alone can complete the work in 12 days. Therefore, B's work rate is:
Work rate of B=1 work12 days=112 work per day
Step 3: Determine A's work rate
To find A's work rate, we can use the combined work rate:
Work rate of A=Work rate of A and B−Work rate of B
Work rate of A=18−112
To subtract these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
18=324,112=224
Work rate of A=324−224=124 work per day
Step 4: Calculate the work done by A and B in 4 days
When A and B work together for 4 days, the amount of work they complete is:
Work done in 4 days=4×Work rate of A and B
Work done in 4 days=4×18=48=12 work
Step 5: Calculate the remaining work
Since the total work is 1, the remaining work after B leaves is:
Remaining work=1−12=12 work
Step 6: Calculate the time taken by A to complete the remaining work
Now, we need to find out how long it will take A to complete the remaining work:
Time taken by A=Remaining workWork rate of A
Time taken by A=12124=12×24=12 days
Conclusion
Thus, A will take 12 days to complete the remaining work after B leaves.
A and B can complete the work together in 8 days. Therefore, their combined work rate is:
Work rate of A and B together=1 work8 days=18 work per day
B alone can complete the work in 12 days. Therefore, B's work rate is:
Work rate of B=1 work12 days=112 work per day
To find A's work rate, we can use the combined work rate:
Work rate of A=Work rate of A and B−Work rate of B
Work rate of A=18−112
To subtract these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
18=324,112=224
Work rate of A=324−224=124 work per day
When A and B work together for 4 days, the amount of work they complete is:
Work done in 4 days=4×Work rate of A and B
Work done in 4 days=4×18=48=12 work
Since the total work is 1, the remaining work after B leaves is:
Remaining work=1−12=12 work
Now, we need to find out how long it will take A to complete the remaining work:
Time taken by A=Remaining workWork rate of A
Time taken by A=12124=12×24=12 days
Thus, A will take 12 days to complete the remaining work after B leaves.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View Solution
Knowledge Check
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
A40B36C45D32A and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
A15 daysB18 daysC16 daysD20 days
A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View Solution