20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?

A

4 days

B

5 days

C

6 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the concept of work done, which can be calculated using the formula:

Work=Number of Workers×Time×Hours Worked per Day

Step 1: Calculate the total work done by the first group of workers.

Given:
- Number of workers (M1) = 20
- Time (D1) = 10 days
- Hours worked per day (T1) = 5 hours

Using the formula:
Total Work=M1×D1×T1
Total Work=20×10×5=1000 worker-hours

Step 2: Set up the equation for the second group of workers.

Now, we need to find out how many days (D2) it will take for the second group of workers to complete the same amount of work.

Given for the second group:
- Number of workers (M2) = 25
- Hours worked per day (T2) = 10 hours
- Days (D2) = ?

Using the same work formula:
Total Work=M2×D2×T2
Since the total work remains the same, we can set up the equation:
1000=25×D2×10

Step 3: Solve for D2.

Rearranging the equation to solve for D2:
1000=250×D2
D2=1000250=4

Conclusion

The time required to complete the work with 25 workers working 10 hours per day is 4 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be

    A7 days
    B8 days
    C10 days
    D12 days
  • Question 2 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Question 3 - Select One

    A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was

    A100
    B300
    C600
    D200