A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?

A

7

B

5

C

9

D

3

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by A and B, and then find out how many days before the work was completed that A left.

Step 1: Determine the work rates of A and B
- A can complete the work in 21 days. Therefore, A's work rate is:
Work rate of A=121 (of the work per day)

- A and B together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A + B=112 (of the work per day)

Step 2: Calculate B's work rate
- To find B's work rate, we subtract A's work rate from their combined work rate:
Work rate of B=Work rate of A + BWork rate of A
Work rate of B=112121

- To perform this subtraction, we need a common denominator, which is 84:
112=784,121=484
Work rate of B=784484=384=128

Step 3: Set up the equation for total work done
- Let A work for x days and B work for the entire 16 days. The total work done can be expressed as:
Work done by A+Work done by B=Total work
(x21)+(1628)=1

Step 4: Convert the work done by B into a common format
- Since 1628=47, we can rewrite the equation:
x21+47=1

Step 5: Solve for x
- To solve for x, we first convert 47 into a fraction with a denominator of 21:
47=1221
x21+1221=1
x+1221=1
x+12=21
x=9

Step 6: Determine how many days before the work was completed A left
- Since A worked for 9 days, and the total time taken to complete the work was 16 days, the number of days before the work was completed that A left is:
169=7

Final Answer
A left the work 7 days before it was completed.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

    A1.125
    B0.625
    C0.375
    D0.875
  • A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

    A1.125
    B0.625
    C0.375
    D0.875
  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16