A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

A

1.125

B

0.625

C

0.375

D

0.875

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Determine the efficiency of A and B together
A and B can complete the task in 1.5 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A + B=11.5=23 (work per day)

Step 2: Determine the efficiency of A alone
A can complete the task in 2.625 days. Therefore, A's efficiency is:
Efficiency of A=12.625=821 (work per day)

Step 3: Calculate the efficiency of B
Using the combined efficiency of A and B, we can find B's efficiency:
Efficiency of B=Efficiency of A + BEfficiency of A
Efficiency of B=23821
To perform this subtraction, we need a common denominator. The least common multiple of 3 and 21 is 21:
23=1421
Now, substituting back:
Efficiency of B=1421821=621=27 (work per day)

Step 4: Determine how long A worked
Let A work for x days. Since the total time taken to complete the task is 2 days, B worked for 2x days. The total work done can be expressed as:
Work done by A+Work done by B=1 (complete work)
(821x)+(27(2x))=1

Step 5: Simplify the equation
First, express 27 in terms of a common denominator with 821:
27=621
Now substitute this back into the equation:
821x+621(2x)=1
Multiply through by 21 to eliminate the fraction:
8x+6(2x)=21
Distributing gives:
8x+126x=21
Combine like terms:
2x+12=21
Subtract 12 from both sides:
2x=9
Divide by 2:
x=4.5

Step 6: Calculate how long A left before the work was completed
Since the total time taken is 2 days, we find how long before the end A left:
Time A left=2x=21.125=0.875 days

Final Answer
A left 0.875 days before the work was completed.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

    A1.125
    B0.625
    C0.375
    D0.875
  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • A and B can complete a task in 25 days. B alone can complete 3313% of the same task in 15 days. In how many days can A alone complete 415th of the same task? /
    A और B किसी कार्य को 25 दिनों में पूरा कर सकते हैं | B इसी कार्य का 3313% भाग अकेले 15 दिनों में पूरा कर सकता है। A इस कार्य का 415th भाग कितने दिनों में पूरा करेगा ?

    A15
    B10
    C18
    D12