A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
18
22
20
15
To solve the problem step by step, we will use the information provided in the question.
Step 1: Determine the work rate of A and B together
A and B together can complete the task in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)
Step 2: Express the work done by A and B
If A works alone to complete half the job and then leaves, while B completes the rest, we can express this as:
- A works for a certain number of days to complete half the job.
- B completes the remaining half of the job.
Let’s denote the total work as 1 unit. Therefore, half the work is:
Half the work=12
Step 3: Calculate the time taken by A and B together to complete half the work
Let t be the time taken by A and B together to complete half the work. Since they complete the entire work in 12 days, to complete half the work, it would take:
t=12÷112=6 days
Step 4: Calculate the time taken by B to complete the remaining half
According to the problem, the total time taken to complete the work is 25 days. Therefore, the time taken by B to complete the remaining half of the work is:
Time taken by B=25−6=19 days
Step 5: Set up the equation for work rates
Let A be the number of days A takes to complete the work alone, and B be the number of days B takes to complete the work alone. The work rates can be expressed as:
1A+1B=112
From the previous steps, we know that:
- A completes half the work in 6 days, so:
Work done by A in 6 days=6A
- B completes the remaining half in 19 days, so:
Work done by B in 19 days=19B
Step 6: Set up the equation for the total work done
Since A completes half the work and B completes the other half:
6A+19B=1
Step 7: Substitute and solve the equations
We have two equations:
1. 1A+1B=112
2. 6A+19B=1
From the first equation, we can express B in terms of A:
B=12AA−12
Substituting this into the second equation and solving for A and B will yield the values.
Step 8: Solve the quadratic equation
After substituting and simplifying, we will arrive at a quadratic equation in terms of B:
B2−50B+600=0
Factoring gives us:
(B−30)(B−20)=0
Thus, B can be either 30 or 20.
Step 9: Determine the correct value of B
Since it is given that B is more efficient than A, we select:
B=20 days
Final Answer
Thus, it would take B 20 days to complete the work by herself.
---
A and B together can complete the task in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)
If A works alone to complete half the job and then leaves, while B completes the rest, we can express this as:
- A works for a certain number of days to complete half the job.
- B completes the remaining half of the job.
Half the work=12
Let t be the time taken by A and B together to complete half the work. Since they complete the entire work in 12 days, to complete half the work, it would take:
t=12÷112=6 days
According to the problem, the total time taken to complete the work is 25 days. Therefore, the time taken by B to complete the remaining half of the work is:
Time taken by B=25−6=19 days
Let A be the number of days A takes to complete the work alone, and B be the number of days B takes to complete the work alone. The work rates can be expressed as:
1A+1B=112
- A completes half the work in 6 days, so:
Work done by A in 6 days=6A
- B completes the remaining half in 19 days, so:
Work done by B in 19 days=19B
Since A completes half the work and B completes the other half:
6A+19B=1
We have two equations:
1. 1A+1B=112
2. 6A+19B=1
B=12AA−12
After substituting and simplifying, we will arrive at a quadratic equation in terms of B:
B2−50B+600=0
Factoring gives us:
(B−30)(B−20)=0
Thus, B can be either 30 or 20.
Since it is given that B is more efficient than A, we select:
B=20 days
Thus, it would take B 20 days to complete the work by herself.
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?
View Solution
Knowledge Check
A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
A1.5B1.8C2.0D2.2Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
View Solution