A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A

18

B

22

C

20

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the information provided in the question.

Step 1: Determine the work rate of A and B together
A and B together can complete the task in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)

Step 2: Express the work done by A and B
If A works alone to complete half the job and then leaves, while B completes the rest, we can express this as:
- A works for a certain number of days to complete half the job.
- B completes the remaining half of the job.

Let’s denote the total work as 1 unit. Therefore, half the work is:
Half the work=12

Step 3: Calculate the time taken by A and B together to complete half the work
Let t be the time taken by A and B together to complete half the work. Since they complete the entire work in 12 days, to complete half the work, it would take:
t=12÷112=6 days

Step 4: Calculate the time taken by B to complete the remaining half
According to the problem, the total time taken to complete the work is 25 days. Therefore, the time taken by B to complete the remaining half of the work is:
Time taken by B=256=19 days

Step 5: Set up the equation for work rates
Let A be the number of days A takes to complete the work alone, and B be the number of days B takes to complete the work alone. The work rates can be expressed as:
1A+1B=112

From the previous steps, we know that:
- A completes half the work in 6 days, so:
Work done by A in 6 days=6A
- B completes the remaining half in 19 days, so:
Work done by B in 19 days=19B

Step 6: Set up the equation for the total work done
Since A completes half the work and B completes the other half:
6A+19B=1

Step 7: Substitute and solve the equations
We have two equations:
1. 1A+1B=112
2. 6A+19B=1

From the first equation, we can express B in terms of A:
B=12AA12

Substituting this into the second equation and solving for A and B will yield the values.

Step 8: Solve the quadratic equation
After substituting and simplifying, we will arrive at a quadratic equation in terms of B:
B250B+600=0
Factoring gives us:
(B30)(B20)=0
Thus, B can be either 30 or 20.

Step 9: Determine the correct value of B
Since it is given that B is more efficient than A, we select:
B=20 days

Final Answer
Thus, it would take B 20 days to complete the work by herself.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

    A1.5
    B1.8
    C2.0
    D2.2
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42