A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
16
32
64
128
The correct Answer is:C
To solve the problem step by step, we will follow the details provided in the video transcript.
Step 1: Determine the efficiencies of A and B
- A and B together can complete the job in 24 days. Therefore, their combined efficiency (E_AB) is:
EAB=124 (work per day)
- A alone can complete the job in 32 days, so A's efficiency (E_A) is:
EA=132 (work per day)
Step 2: Calculate B's efficiency
- We know that:
EAB=EA+EB
- Rearranging gives us B's efficiency (E_B):
EB=EAB−EA=124−132
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 24 and 32 is 96. Thus:
EB=496−396=196
Step 3: Calculate the work done in 8 days by A and B together
- The work done by A and B in 8 days is:
Work done=EAB×time=124×8=824=13
Step 4: Calculate the remaining work
- The total work is considered as 1 unit. Therefore, the remaining work after 8 days is:
Remaining work=1−13=23
Step 5: Calculate the time taken by B to complete the remaining work
- Since B alone will finish the remaining work, we can find the time taken by B:
Time=Remaining workEB=23196=23×96=64 days
Final Answer
- B will take 64 days to complete the remaining job.
---
- A and B together can complete the job in 24 days. Therefore, their combined efficiency (E_AB) is:
EAB=124 (work per day)
- A alone can complete the job in 32 days, so A's efficiency (E_A) is:
EA=132 (work per day)
- We know that:
EAB=EA+EB
- Rearranging gives us B's efficiency (E_B):
EB=EAB−EA=124−132
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 24 and 32 is 96. Thus:
EB=496−396=196
- The work done by A and B in 8 days is:
Work done=EAB×time=124×8=824=13
- The total work is considered as 1 unit. Therefore, the remaining work after 8 days is:
Remaining work=1−13=23
- Since B alone will finish the remaining work, we can find the time taken by B:
Time=Remaining workEB=23196=23×96=64 days
- B will take 64 days to complete the remaining job.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
Knowledge Check
A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
A40B36C45D32A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?
A16 daysB18 daysC20 daysD22 daysA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
A3.8 daysB3.33 daysC2.22 daysD4.3 days
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View SolutionA and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View SolutionA and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
View Solution