Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
In how many days, A alone can complete twice the work?

A

25 days

B

30 days

C

40 days

D

50 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will analyze the work done by A, B, C, and D, and then calculate how many days A alone can complete twice the work.

Step 1: Understand the efficiencies of A, B, C, and D
Let the time taken by A to complete the work be x days.
Then, the time taken by B will be 2x days (since B requires twice the time A requires).

The efficiencies can be calculated as follows:
- Efficiency of A = 1x
- Efficiency of B = 12x

Step 2: Calculate the work done by A and B
A works for 10 days:
- Work done by A in 10 days = 10×1x=10x

B works for 4 more days than A worked. Since A worked for 10 days, B works for 10+4=14 days:
- Work done by B in 14 days = 14×12x=142x=7x

Step 3: Total work done by A and B
Total work done by A and B together:
Total work done=10x+7x=17x

Step 4: Remaining work and work done by C and D
Let the total work be W. The remaining work after A and B is:
W17x

C and D work on alternate days starting with C and complete the remaining work in 30 days. The ratio of their efficiencies is 5:3.

Let the efficiency of C be 5k and the efficiency of D be 3k. In 2 days, they complete:
5k+3k=8k
In 30 days, they complete:
302×8k=15×8k=120k

Step 5: Relate the work done by C and D to the total work
According to the problem, the work done by C and D together is 32% of the total work:
120k=0.32W

Step 6: Calculate the total work W
From the above equation, we can express W:
W=120k0.32=375k

Step 7: Calculate the total work done by A and B
We know:
W=17x+Remaining work
The remaining work is:
W17x=375k17x

Step 8: Calculate the efficiency of A
We have:
17x+120k=375k
This gives us:
17x=375k120k=255k
Thus:
x=17255k=172551k

Step 9: Calculate the time taken by A to complete twice the work
The efficiency of A is 1x, so the time taken by A to complete twice the work 2W is:
Time=2WEfficiency of A=2×375k1x=2×375k×x
Substituting x:
=2×375k×172551k=2×375×17255
Calculating this gives:
=2×375×17255=12750255=50

Final Answer
A alone can complete twice the work in 50 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • Question 2 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)
  • Question 3 - Select One

    A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16