Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
In how many days, A alone can complete twice the work?
25 days
30 days
40 days
50 days
The correct Answer is:D
To solve the problem step by step, we will analyze the work done by A, B, C, and D, and then calculate how many days A alone can complete twice the work.
Step 1: Understand the efficiencies of A, B, C, and D
Let the time taken by A to complete the work be x days.
Then, the time taken by B will be 2x days (since B requires twice the time A requires).
The efficiencies can be calculated as follows:
- Efficiency of A = 1x
- Efficiency of B = 12x
Step 2: Calculate the work done by A and B
A works for 10 days:
- Work done by A in 10 days = 10×1x=10x
B works for 4 more days than A worked. Since A worked for 10 days, B works for 10+4=14 days:
- Work done by B in 14 days = 14×12x=142x=7x
Step 3: Total work done by A and B
Total work done by A and B together:
Total work done=10x+7x=17x
Step 4: Remaining work and work done by C and D
Let the total work be W. The remaining work after A and B is:
W−17x
C and D work on alternate days starting with C and complete the remaining work in 30 days. The ratio of their efficiencies is 5:3.
Let the efficiency of C be 5k and the efficiency of D be 3k. In 2 days, they complete:
5k+3k=8k
In 30 days, they complete:
302×8k=15×8k=120k
Step 5: Relate the work done by C and D to the total work
According to the problem, the work done by C and D together is 32% of the total work:
120k=0.32W
Step 6: Calculate the total work W
From the above equation, we can express W:
W=120k0.32=375k
Step 7: Calculate the total work done by A and B
We know:
W=17x+Remaining work
The remaining work is:
W−17x=375k−17x
Step 8: Calculate the efficiency of A
We have:
17x+120k=375k
This gives us:
17x=375k−120k=255k
Thus:
x=17255k=17255⋅1k
Step 9: Calculate the time taken by A to complete twice the work
The efficiency of A is 1x, so the time taken by A to complete twice the work 2W is:
Time=2WEfficiency of A=2×375k1x=2×375k×x
Substituting x:
=2×375k×17255⋅1k=2×375×17255
Calculating this gives:
=2×375×17255=12750255=50
Final Answer
A alone can complete twice the work in 50 days.
Let the time taken by A to complete the work be x days.
Then, the time taken by B will be 2x days (since B requires twice the time A requires).
- Efficiency of A = 1x
- Efficiency of B = 12x
A works for 10 days:
- Work done by A in 10 days = 10×1x=10x
- Work done by B in 14 days = 14×12x=142x=7x
Total work done by A and B together:
Total work done=10x+7x=17x
Let the total work be W. The remaining work after A and B is:
W−17x
5k+3k=8k
In 30 days, they complete:
302×8k=15×8k=120k
According to the problem, the work done by C and D together is 32% of the total work:
120k=0.32W
From the above equation, we can express W:
W=120k0.32=375k
We know:
W=17x+Remaining work
The remaining work is:
W−17x=375k−17x
We have:
17x+120k=375k
This gives us:
17x=375k−120k=255k
Thus:
x=17255k=17255⋅1k
The efficiency of A is 1x, so the time taken by A to complete twice the work 2W is:
Time=2WEfficiency of A=2×375k1x=2×375k×x
Substituting x:
=2×375k×17255⋅1k=2×375×17255
Calculating this gives:
=2×375×17255=12750255=50
A alone can complete twice the work in 50 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View Solution
Knowledge Check
- Question 1 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A6623B3313C1623D1427 - Question 2 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A66(2/3)B33(1/3)C16(2/3)D14(2/7) - Question 3 - Select One
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16
A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View SolutionA, B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View Solution