A can complete a work in 20 days and B can complete the same work in 16 days. C's work efficiency is 3313% of the work efficiency of A and B together. In how many day A, B and C can complete the work if they work alternatively starting from A followed by B and C?
1845days
18 days
14 days
1945days
The correct Answer is:D
To solve the problem step by step, we will follow these calculations:
Step 1: Calculate the work done by A and B
- A can complete the work in 20 days. Therefore, A's work efficiency is:
Efficiency of A=120 (work/day)
- B can complete the work in 16 days. Therefore, B's work efficiency is:
Efficiency of B=116 (work/day)
Step 2: Calculate the total efficiency of A and B
- To find the total efficiency of A and B together, we need to find a common denominator:
Efficiency of A+Efficiency of B=120+116
- The LCM of 20 and 16 is 80. Converting the efficiencies:
120=480,116=580
- Therefore, the total efficiency of A and B is:
Total Efficiency of A and B=480+580=980 (work/day)
Step 3: Calculate C's efficiency
- C's efficiency is given as 3313% of the total efficiency of A and B:
C′s efficiency=33.33100×980=13×980=380 (work/day)
Step 4: Calculate the combined efficiency of A, B, and C
- The combined efficiency of A, B, and C working together is:
Total Efficiency of A, B, and C=480+580+380=1280=320 (work/day)
Step 5: Determine the work done in one complete cycle
- In one complete cycle (A, B, C), the work done is:
Work done in one cycle=Efficiency of A+Efficiency of B+Efficiency of C=480+580+380=1280=320
- The total work is 1 (the entire work), and in one cycle, they complete 320 of the work.
Step 6: Calculate the number of cycles needed to complete the work
- To find how many cycles are needed to complete the work:
Number of cycles=1320=203 cycles
Step 7: Calculate the total time taken for the cycles
- Each cycle takes 3 days (A, B, C):
Total days for complete cycles=3×⌊203⌋=3×6=18 days
Step 8: Calculate the remaining work after 18 days
- In 18 days, they complete:
Work done=6×320=1820=910
- Remaining work is:
1−910=110
Step 9: Determine who works next and how much time it takes
- On the 19th day, A works and completes:
Work done by A on the 19th day=120
- Since 120>110, A will finish the remaining work on the 19th day.
Final Answer
- Therefore, the total time taken by A, B, and C to complete the work is:
18 days+A's work on the 19th day=1915 days
- The answer is 1945 days.
- A can complete the work in 20 days. Therefore, A's work efficiency is:
Efficiency of A=120 (work/day)
- B can complete the work in 16 days. Therefore, B's work efficiency is:
Efficiency of B=116 (work/day)
- To find the total efficiency of A and B together, we need to find a common denominator:
Efficiency of A+Efficiency of B=120+116
- The LCM of 20 and 16 is 80. Converting the efficiencies:
120=480,116=580
- Therefore, the total efficiency of A and B is:
Total Efficiency of A and B=480+580=980 (work/day)
- C's efficiency is given as 3313% of the total efficiency of A and B:
C′s efficiency=33.33100×980=13×980=380 (work/day)
- The combined efficiency of A, B, and C working together is:
Total Efficiency of A, B, and C=480+580+380=1280=320 (work/day)
- In one complete cycle (A, B, C), the work done is:
Work done in one cycle=Efficiency of A+Efficiency of B+Efficiency of C=480+580+380=1280=320
- The total work is 1 (the entire work), and in one cycle, they complete 320 of the work.
- To find how many cycles are needed to complete the work:
Number of cycles=1320=203 cycles
- Each cycle takes 3 days (A, B, C):
Total days for complete cycles=3×⌊203⌋=3×6=18 days
- In 18 days, they complete:
Work done=6×320=1820=910
- Remaining work is:
1−910=110
- On the 19th day, A works and completes:
Work done by A on the 19th day=120
- Since 120>110, A will finish the remaining work on the 19th day.
- Therefore, the total time taken by A, B, and C to complete the work is:
18 days+A's work on the 19th day=1915 days
- The answer is 1945 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View Solution
Knowledge Check
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 daysA and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?
A8B16C12D15
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
View SolutionA can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
View SolutionA can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
View Solution