Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
E and F together work for 12 days, then they are replaced by A and B and they completed the remaining work in 10 days. If the ratio of efficiencies of E and F is 3 : 2 and E and F together completed the whole work then find the difference between the part of work done by E and the part of work done by F in one day?

A

A)1200

B

B)1150

C

C)1300

D

D)175

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will break it down into manageable parts.

Step 1: Understanding the Work Distribution
- Let A's time to complete the work be x days.
- Then, B's time to complete the work is 2x days (since B requires twice the time of A).
- The efficiencies of A and B can be expressed as:
- Efficiency of A = 1x
- Efficiency of B = 12x

Step 2: Work Done by A and B
- A works for 10 days, so the work done by A in 10 days is:
Work by A=10×1x=10x
- B works for 10+4=14 days (4 more days than A), so the work done by B is:
Work by B=14×12x=142x=7x

Step 3: Total Work Done by A and B
- Total work done by A and B together:
Total Work by A and B=10x+7x=17x

Step 4: Remaining Work
- The total work is represented as 100%. We know that C and D together completed 32% of the work in 30 days. Therefore, the remaining work done by A and B is:
Remaining Work=100%32%=68%
- This can be expressed in terms of total work W:
17x=0.68W

Step 5: Finding Total Work W
- Given that C and D together completed 120 units of work (32% of total work):
0.32W=120W=1200.32=375

Step 6: Work Done by A and B
- Substitute W into the equation:
17x=0.68×375
17x=25517=255xx=17255=115

Step 7: Finding Efficiencies
- Now, substituting x back:
- Efficiency of A = 1x=15
- Efficiency of B = 12x=7.5

Step 8: Work Done by E and F
- Let the efficiencies of E and F be 3y and 2y respectively.
- They work together for 12 days:
Work by E and F=(3y+2y)×12=5y×12=60y
- After E and F, A and B complete the remaining work in 10 days:
Work by A and B in 10 days=(15+7.5)×10=225
- Total work done by E and F plus A and B must equal total work:
60y+225=37560y=150y=15060=2.5

Step 9: Finding Efficiencies of E and F
- Efficiency of E = 3y=3×2.5=7.5
- Efficiency of F = 2y=2×2.5=5

Step 10: Work Done in One Day
- Work done by E in one day:
Work by E in one day=7.5375=150
- Work done by F in one day:
Work by F in one day=5375=175

Step 11: Finding the Difference
- Difference in work done by E and F in one day:
Difference=150175
- Finding a common denominator (150):
=31502150=1150

Final Answer
The difference between the part of work done by E and the part of work done by F in one day is:
1150

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    B is 20% more efficient than A. B started the work & do it for
    x days. And then B is replaced by A, A completed the
    remaining work in x+8 days. Ratio of work done by A & B is
    3:2 IN how many days A & B working together complete
    the whole work?

    A131117days
    B12711days
    C13711days
    D12813days
  • Question 2 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A6623
    B3313
    C1623
    D1427
  • Question 3 - Select One

    Each of A, B, C and D need a umique
    time to do a certain work. A can do the work in x days and B can
    do the work in 2x days. A started the work and do it for 2229 days
    then he is replaced by B and B completed remaining work in same
    time as C and D together can complete the whole work.
    The ratio of the efficiency of C and D is 4:5. If C and D work for
    alternative days starting form C then they can do the total work
    in 4412 days.

    A66(2/3)
    B33(1/3)
    C16(2/3)
    D14(2/7)