Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
E and F together work for 12 days, then they are replaced by A and B and they completed the remaining work in 10 days. If the ratio of efficiencies of E and F is 3 : 2 and E and F together completed the whole work then find the difference between the part of work done by E and the part of work done by F in one day?
A)1200
B)1150
C)1300
D)175
The correct Answer is:B
To solve the problem step by step, we will break it down into manageable parts.
Step 1: Understanding the Work Distribution
- Let A's time to complete the work be x days.
- Then, B's time to complete the work is 2x days (since B requires twice the time of A).
- The efficiencies of A and B can be expressed as:
- Efficiency of A = 1x
- Efficiency of B = 12x
Step 2: Work Done by A and B
- A works for 10 days, so the work done by A in 10 days is:
Work by A=10×1x=10x
- B works for 10+4=14 days (4 more days than A), so the work done by B is:
Work by B=14×12x=142x=7x
Step 3: Total Work Done by A and B
- Total work done by A and B together:
Total Work by A and B=10x+7x=17x
Step 4: Remaining Work
- The total work is represented as 100%. We know that C and D together completed 32% of the work in 30 days. Therefore, the remaining work done by A and B is:
Remaining Work=100%−32%=68%
- This can be expressed in terms of total work W:
17x=0.68W
Step 5: Finding Total Work W
- Given that C and D together completed 120 units of work (32% of total work):
0.32W=120⟹W=1200.32=375
Step 6: Work Done by A and B
- Substitute W into the equation:
17x=0.68×375
17x=255⟹17=255x⟹x=17255=115
Step 7: Finding Efficiencies
- Now, substituting x back:
- Efficiency of A = 1x=15
- Efficiency of B = 12x=7.5
Step 8: Work Done by E and F
- Let the efficiencies of E and F be 3y and 2y respectively.
- They work together for 12 days:
Work by E and F=(3y+2y)×12=5y×12=60y
- After E and F, A and B complete the remaining work in 10 days:
Work by A and B in 10 days=(15+7.5)×10=225
- Total work done by E and F plus A and B must equal total work:
60y+225=375⟹60y=150⟹y=15060=2.5
Step 9: Finding Efficiencies of E and F
- Efficiency of E = 3y=3×2.5=7.5
- Efficiency of F = 2y=2×2.5=5
Step 10: Work Done in One Day
- Work done by E in one day:
Work by E in one day=7.5375=150
- Work done by F in one day:
Work by F in one day=5375=175
Step 11: Finding the Difference
- Difference in work done by E and F in one day:
Difference=150−175
- Finding a common denominator (150):
=3150−2150=1150
Final Answer
The difference between the part of work done by E and the part of work done by F in one day is:
1150
- Let A's time to complete the work be x days.
- Then, B's time to complete the work is 2x days (since B requires twice the time of A).
- The efficiencies of A and B can be expressed as:
- Efficiency of A = 1x
- Efficiency of B = 12x
- A works for 10 days, so the work done by A in 10 days is:
Work by A=10×1x=10x
- B works for 10+4=14 days (4 more days than A), so the work done by B is:
Work by B=14×12x=142x=7x
- Total work done by A and B together:
Total Work by A and B=10x+7x=17x
- The total work is represented as 100%. We know that C and D together completed 32% of the work in 30 days. Therefore, the remaining work done by A and B is:
Remaining Work=100%−32%=68%
- This can be expressed in terms of total work W:
17x=0.68W
- Given that C and D together completed 120 units of work (32% of total work):
0.32W=120⟹W=1200.32=375
- Substitute W into the equation:
17x=0.68×375
17x=255⟹17=255x⟹x=17255=115
- Now, substituting x back:
- Efficiency of A = 1x=15
- Efficiency of B = 12x=7.5
- Let the efficiencies of E and F be 3y and 2y respectively.
- They work together for 12 days:
Work by E and F=(3y+2y)×12=5y×12=60y
- After E and F, A and B complete the remaining work in 10 days:
Work by A and B in 10 days=(15+7.5)×10=225
- Total work done by E and F plus A and B must equal total work:
60y+225=375⟹60y=150⟹y=15060=2.5
- Efficiency of E = 3y=3×2.5=7.5
- Efficiency of F = 2y=2×2.5=5
- Work done by E in one day:
Work by E in one day=7.5375=150
- Work done by F in one day:
Work by F in one day=5375=175
- Difference in work done by E and F in one day:
Difference=150−175
- Finding a common denominator (150):
=3150−2150=1150
The difference between the part of work done by E and the part of work done by F in one day is:
1150
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionA and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?
View Solution
Knowledge Check
- Question 1 - Select One
B is 20% more efficient than A. B started the work & do it for
x days. And then B is replaced by A, A completed the
remaining work in x+8 days. Ratio of work done by A & B is
3:2 IN how many days A & B working together complete
the whole work?A131117daysB12711daysC13711daysD12813days - Question 2 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A6623B3313C1623D1427 - Question 3 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A66(2/3)B33(1/3)C16(2/3)D14(2/7)
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA, B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View SolutionA and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
View Solution