Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, B and C working together completed 13rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked?
12 days
10 days
15 days
4 days
The correct Answer is:A
To solve the problem step by step, let's break it down systematically.
Step 1: Determine the efficiencies of A, B, C, and D
- Let the efficiency of B be x.
- Since A's efficiency is 20% more than B's, we have:
A=x+0.2x=1.2x
- Given that B can complete work X in 36 days, the total work W can be calculated as:
W=Efficiency×Time=x×36
- Therefore, the total work W=36x.
Step 2: Calculate the total work in terms of B's efficiency
- From the information given, we can also express the total work as:
W=180(as derived from the video)
- Setting these equal gives:
36x=180⟹x=5
- Thus, the efficiencies are:
B=5,A=1.2×5=6,and we need to find C's efficiency.
Step 3: Find C's efficiency
- From the work done by B and C together for 10 days:
Work done by B and C in 10 days=10(B+C)=10(5+C)
- The remaining work is completed by A in 15 days:
Remaining work=15A=15×6=90
- Therefore, the total work can also be expressed as:
10(5+C)+90=180
50+10C+90=180⟹10C=40⟹C=4
Step 4: Efficiency of D
- A and C work together for 12 days, and then B completes the remaining work in 16 days.
- The total work done by A and C in 12 days:
12(A+C)=12(6+4)=120
- The remaining work done by B alone in 16 days:
16B=16×5=80
- Therefore, the total work for Y is:
120+80=200
Step 5: Calculate D's efficiency
- D completes both works in 38 days:
180D+200D=38⟹380D=38⟹D=10
Step 6: Work done by A, B, and C together
- A, B, and C together complete 13 of work X:
Work done=13×180=60
- Their combined efficiency:
A+B+C=6+5+4=15
- Time taken to complete 60 work:
Time=6015=4 days
Step 7: Remaining work done by B and D
- Remaining work after A, B, and C completed 13:
Remaining work=180−60=120
- B and D together work on the remaining work:
Efficiency of B and D=5+10=15
- Time taken to complete the remaining work:
Time=12015=8 days
Step 8: Total days worked by B
- B worked for:
4 days (with A and C)+8 days (with D)=12 days
Final Answer
B worked for 12 days.
- Let the efficiency of B be x.
- Since A's efficiency is 20% more than B's, we have:
A=x+0.2x=1.2x
- Given that B can complete work X in 36 days, the total work W can be calculated as:
W=Efficiency×Time=x×36
- Therefore, the total work W=36x.
- From the information given, we can also express the total work as:
W=180(as derived from the video)
- Setting these equal gives:
36x=180⟹x=5
- Thus, the efficiencies are:
B=5,A=1.2×5=6,and we need to find C's efficiency.
- From the work done by B and C together for 10 days:
Work done by B and C in 10 days=10(B+C)=10(5+C)
- The remaining work is completed by A in 15 days:
Remaining work=15A=15×6=90
- Therefore, the total work can also be expressed as:
10(5+C)+90=180
50+10C+90=180⟹10C=40⟹C=4
- A and C work together for 12 days, and then B completes the remaining work in 16 days.
- The total work done by A and C in 12 days:
12(A+C)=12(6+4)=120
- The remaining work done by B alone in 16 days:
16B=16×5=80
- Therefore, the total work for Y is:
120+80=200
- D completes both works in 38 days:
180D+200D=38⟹380D=38⟹D=10
- A, B, and C together complete 13 of work X:
Work done=13×180=60
- Their combined efficiency:
A+B+C=6+5+4=15
- Time taken to complete 60 work:
Time=6015=4 days
- Remaining work after A, B, and C completed 13:
Remaining work=180−60=120
- B and D together work on the remaining work:
Efficiency of B and D=5+10=15
- Time taken to complete the remaining work:
Time=12015=8 days
- B worked for:
4 days (with A and C)+8 days (with D)=12 days
B worked for 12 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View Solution
Knowledge Check
A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 daysA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB8 daysC9 daysD5 daysA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
A75B25C45D60
A and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View Solution