Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, B and C working together completed 13rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked?

A

12 days

B

10 days

C

15 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down systematically.

Step 1: Determine the efficiencies of A, B, C, and D
- Let the efficiency of B be x.
- Since A's efficiency is 20% more than B's, we have:
A=x+0.2x=1.2x
- Given that B can complete work X in 36 days, the total work W can be calculated as:
W=Efficiency×Time=x×36
- Therefore, the total work W=36x.

Step 2: Calculate the total work in terms of B's efficiency
- From the information given, we can also express the total work as:
W=180(as derived from the video)
- Setting these equal gives:
36x=180x=5
- Thus, the efficiencies are:
B=5,A=1.2×5=6,and we need to find C's efficiency.

Step 3: Find C's efficiency
- From the work done by B and C together for 10 days:
Work done by B and C in 10 days=10(B+C)=10(5+C)
- The remaining work is completed by A in 15 days:
Remaining work=15A=15×6=90
- Therefore, the total work can also be expressed as:
10(5+C)+90=180
50+10C+90=18010C=40C=4

Step 4: Efficiency of D
- A and C work together for 12 days, and then B completes the remaining work in 16 days.
- The total work done by A and C in 12 days:
12(A+C)=12(6+4)=120
- The remaining work done by B alone in 16 days:
16B=16×5=80
- Therefore, the total work for Y is:
120+80=200

Step 5: Calculate D's efficiency
- D completes both works in 38 days:
180D+200D=38380D=38D=10

Step 6: Work done by A, B, and C together
- A, B, and C together complete 13 of work X:
Work done=13×180=60
- Their combined efficiency:
A+B+C=6+5+4=15
- Time taken to complete 60 work:
Time=6015=4 days

Step 7: Remaining work done by B and D
- Remaining work after A, B, and C completed 13:
Remaining work=18060=120
- B and D together work on the remaining work:
Efficiency of B and D=5+10=15
- Time taken to complete the remaining work:
Time=12015=8 days

Step 8: Total days worked by B
- B worked for:
4 days (with A and C)+8 days (with D)=12 days

Final Answer
B worked for 12 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A75
    B25
    C45
    D60