A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete 58th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete 512th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
The job is completed in the following manner: A and B work on day 1, B and C work on day 2, C and D work on day 3, D and A work on day 4 and so on. How long will it take for the job to be completed in this manner?

A

30 days

B

24 days

C

18 days

D

15 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will analyze the information given about the work done by A, B, C, and D, and calculate the total time taken to complete the job.

Step 1: Determine the efficiencies of A and B
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day

Step 2: Calculate the time taken by A and B
Let the time taken by B to complete the job be x days. Therefore, the time taken by A is x80 days. Since A is thrice as efficient as B, we can set up the equation based on their efficiencies:

Total work=Efficiency×Time

For A:
Total work=3×(x80)

For B:
Total work=1×x

Equating the two expressions for total work:
3(x80)=x
3x240=x
2x=240
x=120

So, B takes 120 days to complete the job, and A takes:
12080=40 days

Step 3: Calculate the total work
Using B's time:
Total work=1×120=120 units

Step 4: Work done by A and B together
A and B complete 58 of the job:
Work done=58×120=75 units

Remaining work:
12075=45 units

Step 5: Work done by B and C
B and C complete the remaining work in 15 days:
Let C's efficiency be c. The total efficiency of B and C is:
1+c
The work done in 15 days is:
15(1+c)=45
1+c=3c=2

Step 6: Work done by A and D
Next, A and B complete 512 of the job:
Work done=512×120=50 units

Remaining work:
12050=70 units

A and D complete this remaining work in 10 days:
Let D's efficiency be d. The total efficiency of A and D is:
3+d
The work done in 10 days is:
10(3+d)=70
3+d=7d=4

Step 7: Summary of efficiencies
- Efficiency of A = 3
- Efficiency of B = 1
- Efficiency of C = 2
- Efficiency of D = 4

Step 8: Work done in a cycle of 4 days
Now, we calculate the work done in the cycle of 4 days:
1. Day 1: A + B = 3 + 1 = 4 units
2. Day 2: B + C = 1 + 2 = 3 units
3. Day 3: C + D = 2 + 4 = 6 units
4. Day 4: D + A = 4 + 3 = 7 units

Total work done in 4 days:
4+3+6+7=20 units

Step 9: Total days to complete the job
Total work = 120 units. The number of complete cycles needed:
12020=6 cycles
Each cycle takes 4 days:
6×4=24 days

Thus, the total time taken to complete the job is 24 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in

    A14 days
    B13 days
    C20 days
    D15 days
  • A is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in

    A14 days
    B13 days
    C20 days
    D15 days
  • A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?

    A1014
    B1134
    C1114
    D1113