A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete 58th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete 512th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
The job is completed in the following manner: A and B work on day 1, B and C work on day 2, C and D work on day 3, D and A work on day 4 and so on. How long will it take for the job to be completed in this manner?
30 days
24 days
18 days
15 days
The correct Answer is:B
To solve the problem step by step, we will analyze the information given about the work done by A, B, C, and D, and calculate the total time taken to complete the job.
Step 1: Determine the efficiencies of A and B
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day
Step 2: Calculate the time taken by A and B
Let the time taken by B to complete the job be x days. Therefore, the time taken by A is x−80 days. Since A is thrice as efficient as B, we can set up the equation based on their efficiencies:
Total work=Efficiency×Time
For A:
Total work=3×(x−80)
For B:
Total work=1×x
Equating the two expressions for total work:
3(x−80)=x
3x−240=x
2x=240
x=120
So, B takes 120 days to complete the job, and A takes:
120−80=40 days
Step 3: Calculate the total work
Using B's time:
Total work=1×120=120 units
Step 4: Work done by A and B together
A and B complete 58 of the job:
Work done=58×120=75 units
Remaining work:
120−75=45 units
Step 5: Work done by B and C
B and C complete the remaining work in 15 days:
Let C's efficiency be c. The total efficiency of B and C is:
1+c
The work done in 15 days is:
15(1+c)=45
1+c=3⟹c=2
Step 6: Work done by A and D
Next, A and B complete 512 of the job:
Work done=512×120=50 units
Remaining work:
120−50=70 units
A and D complete this remaining work in 10 days:
Let D's efficiency be d. The total efficiency of A and D is:
3+d
The work done in 10 days is:
10(3+d)=70
3+d=7⟹d=4
Step 7: Summary of efficiencies
- Efficiency of A = 3
- Efficiency of B = 1
- Efficiency of C = 2
- Efficiency of D = 4
Step 8: Work done in a cycle of 4 days
Now, we calculate the work done in the cycle of 4 days:
1. Day 1: A + B = 3 + 1 = 4 units
2. Day 2: B + C = 1 + 2 = 3 units
3. Day 3: C + D = 2 + 4 = 6 units
4. Day 4: D + A = 4 + 3 = 7 units
Total work done in 4 days:
4+3+6+7=20 units
Step 9: Total days to complete the job
Total work = 120 units. The number of complete cycles needed:
12020=6 cycles
Each cycle takes 4 days:
6×4=24 days
Thus, the total time taken to complete the job is 24 days.
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day
Let the time taken by B to complete the job be x days. Therefore, the time taken by A is x−80 days. Since A is thrice as efficient as B, we can set up the equation based on their efficiencies:
Total work=3×(x−80)
Total work=1×x
3(x−80)=x
3x−240=x
2x=240
x=120
120−80=40 days
Using B's time:
Total work=1×120=120 units
A and B complete 58 of the job:
Work done=58×120=75 units
120−75=45 units
B and C complete the remaining work in 15 days:
Let C's efficiency be c. The total efficiency of B and C is:
1+c
The work done in 15 days is:
15(1+c)=45
1+c=3⟹c=2
Next, A and B complete 512 of the job:
Work done=512×120=50 units
120−50=70 units
Let D's efficiency be d. The total efficiency of A and D is:
3+d
The work done in 10 days is:
10(3+d)=70
3+d=7⟹d=4
- Efficiency of A = 3
- Efficiency of B = 1
- Efficiency of C = 2
- Efficiency of D = 4
Now, we calculate the work done in the cycle of 4 days:
1. Day 1: A + B = 3 + 1 = 4 units
2. Day 2: B + C = 1 + 2 = 3 units
3. Day 3: C + D = 2 + 4 = 6 units
4. Day 4: D + A = 4 + 3 = 7 units
4+3+6+7=20 units
Total work = 120 units. The number of complete cycles needed:
12020=6 cycles
Each cycle takes 4 days:
6×4=24 days
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Knowledge Check
A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 daysA is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 daysA is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
A1014B1134C1114D1113
P is thrice as good a workman as Q and therefore able to finish a Job in 48 days less than . Working together, they can do it in :
View SolutionA, B and C can complete a work in 2h. If A does the job alone in 6h and B in 5h, how long will it take for C to finish the job alone ?
View SolutionA and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?
View SolutionHow many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?
View SolutionA work is alone by A and B in 4 days while A alone completes the job in 12 days, then in how many days will B alone complete ?
View Solution