How many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?
20
21
45
63
The correct Answer is:D
To solve the problem, we will follow these steps:
Step 1: Determine the total work in terms of man-days.
Given that 15 men can complete 13 of the job in 7 days, we can calculate the total work in man-days.
Work done by 15 men in 7 days=15 men×7 days=105 man-days
Since this amount of work corresponds to 13 of the total job, we can find the total work (W) as follows:
W=105 man-days×3=315 man-days
Step 2: Calculate the number of men needed to complete the job in 5 days.
Now, we need to find out how many men (M) are required to complete the total work (315 man-days) in 5 days.
Using the formula for work:
Work=Number of Men×Days
We can rearrange this to find the number of men:
M=WD
Substituting the values we have:
M=315 man-days5 days=63 men
Final Answer:
Therefore, 63 men are needed to complete the job in 5 days.
---
Given that 15 men can complete 13 of the job in 7 days, we can calculate the total work in man-days.
Now, we need to find out how many men (M) are required to complete the total work (315 man-days) in 5 days.
Therefore, 63 men are needed to complete the job in 5 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II
45 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
Knowledge Check
How many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?
A20B21C45D6324 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D5015 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View Solution12 men and 16 women can complete a jon in 5 days. 13 men and 24 women can complete the same job in 4 days. How long, in days, will 5 men and 10 women take to complete the same job?
View SolutionA company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
View Solution