A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?
20 days
60 days
30 days
40 days
The correct Answer is:C
To solve the problem, we need to determine how long A would take to complete the job alone, given the combined work rates of A, B, and C.
1. Identify the Work Rates:
- A and B can complete the job in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (jobs per day)
- B and C can complete the job in 15 days. Therefore, their combined work rate is:
Work rate of B and C=115 (jobs per day)
- C and A can complete the job in 20 days. Therefore, their combined work rate is:
Work rate of C and A=120 (jobs per day)
2. Set Up the Equations:
- Let the work rates of A, B, and C be represented as a, b, and c respectively. We can write the following equations based on the combined work rates:
a+b=112(1)
b+c=115(2)
c+a=120(3)
3. Add All Three Equations:
- Adding equations (1), (2), and (3):
(a+b)+(b+c)+(c+a)=112+115+120
- This simplifies to:
2a+2b+2c=112+115+120
- Dividing the entire equation by 2 gives:
a+b+c=124 (4)
4. Calculate the Right Side:
- To find the sum of the fractions on the right side, we need to find the LCM of 12, 15, and 20:
- LCM(12, 15, 20) = 60
- Convert each fraction:
112=560,115=460,120=360
- Adding these gives:
5+4+360=1260=15
- Thus, from equation (4):
a+b+c=15
5. Find Individual Work Rates:
- Now we can find the work rate of A:
- From equation (1): b=112−a
- From equation (2): c=115−b
- Substitute b in terms of a into equation (2):
c=115−(112−a)=a+115−112
- Substitute c into equation (3) and solve for a:
c+a=120
- After some algebra, we can isolate a and find:
a=130
6. Calculate the Time Taken by A:
- Since a represents the work rate of A, the time taken by A to complete the job alone is:
Time taken by A=1a=30 days
Final Answer:
A would take 30 days to complete the job alone.
- A and B can complete the job in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (jobs per day)
- B and C can complete the job in 15 days. Therefore, their combined work rate is:
Work rate of B and C=115 (jobs per day)
- C and A can complete the job in 20 days. Therefore, their combined work rate is:
Work rate of C and A=120 (jobs per day)
- Let the work rates of A, B, and C be represented as a, b, and c respectively. We can write the following equations based on the combined work rates:
a+b=112(1)
b+c=115(2)
c+a=120(3)
- Adding equations (1), (2), and (3):
(a+b)+(b+c)+(c+a)=112+115+120
- This simplifies to:
2a+2b+2c=112+115+120
- Dividing the entire equation by 2 gives:
a+b+c=124 (4)
- To find the sum of the fractions on the right side, we need to find the LCM of 12, 15, and 20:
- LCM(12, 15, 20) = 60
- Convert each fraction:
112=560,115=460,120=360
- Adding these gives:
5+4+360=1260=15
- Thus, from equation (4):
a+b+c=15
- Now we can find the work rate of A:
- From equation (1): b=112−a
- From equation (2): c=115−b
- Substitute b in terms of a into equation (2):
c=115−(112−a)=a+115−112
- Substitute c into equation (3) and solve for a:
c+a=120
- After some algebra, we can isolate a and find:
a=130
- Since a represents the work rate of A, the time taken by A to complete the job alone is:
Time taken by A=1a=30 days
A would take 30 days to complete the job alone.
Similar Questions
A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
View Solution
Knowledge Check
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
A24 daysB32 daysC40 daysD48 daysA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
A10 daysB20 daysC30 daysD40 daysA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
A60 daysB120 daysC80 daysD30 days
A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. Calone can do the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View Solution