Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A person E starts the work 'X' and leave after 12 days, then B and C complete the remaining work in 8 days. What is the ratio of number of days taken by A and E together to complete the work 'X' to the number of days taken by D, B and C together to complete the both work 'X' and 'Y'.

A

3:5

B

5:3

C

8:7

D

1:2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down into manageable parts:

Step 1: Determine the efficiencies of A and B
Given that the efficiency of A is 20% more than that of B, if we let the efficiency of B be EB=5, then:
EA=EB+0.2×EB=5+1=6
Thus, the efficiencies are:
- Efficiency of A = 6
- Efficiency of B = 5

Step 2: Calculate the total work for work X
B can complete work X in 36 days. Therefore, the total work WX can be calculated as:
WX=EB×Time taken by B=5×36=180

Step 3: Find the efficiency of C
B and C together worked for 10 days, and A completed the remaining work in 15 days. The total work done by A in 15 days is:
Work done by A=EA×Time taken by A=6×15=90
Thus, the work done by B and C together in 10 days is:
WXWork done by A=18090=90
Let the efficiency of C be EC. Therefore:
(EB+EC)×10=90
Substituting EB=5:
(5+EC)×10=905+EC=9EC=4

Step 4: Calculate the total work for work Y
A and C together worked for 12 days, and B completed the remaining work in 16 days. The total work done by A and C in 12 days is:
Work done by A and C=(EA+EC)×12=(6+4)×12=120
Thus, the remaining work done by B in 16 days is:
WY120=EB×16WY120=5×16=80WY=200

Step 5: Calculate the efficiency of D
D completed both works X and Y in 38 days:
Total work=WX+WY=180+200=380
Let the efficiency of D be ED:
ED×38=380ED=38038=10

Step 6: Determine the efficiency of E
E starts work X and leaves after 12 days. The remaining work is completed by B and C in 8 days. The total work done by B and C in 8 days is:
(EB+EC)×8=(5+4)×8=72
Thus, the work done by E in 12 days is:
WX72=18072=108
So, the efficiency of E can be calculated as:
E×12=108E=10812=9

Step 7: Calculate the ratio of days taken by A and E together to complete work X
The combined efficiency of A and E is:
EA+EE=6+9=15
The time taken by A and E together to complete work X is:
Time=WXEA+EE=18015=12 days

Step 8: Calculate the time taken by D, B, and C together to complete both works X and Y
The combined efficiency of D, B, and C is:
ED+EB+EC=10+5+4=19
The total work for both X and Y is 380, so the time taken is:
Time=WX+WYED+EB+EC=38019=20 days

Step 9: Calculate the final ratio
The required ratio of the number of days taken by A and E together to complete work X to the number of days taken by D, B, and C together to complete both works X and Y is:
Ratio=1220=35

Final Answer
The ratio of the number of days taken by A and E together to complete work X to the number of days taken by D, B, and C together to complete both works X and Y is 35.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A75
    B25
    C45
    D60