B alone can complete a piece of work in 36 days while D alone can complete same piece of work in 25 days. C is 50 % more efficient than B and A is 20% less efficient than C. If all four starts working together (B & C are working with 56% & 20% more efficiency respectively than their usual efficiency), then in how many days the work will be completed?

A

A)12 days

B

B)18 days

C

C)15 days

D

D)6 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break down the information given and calculate the required values.

Step 1: Determine the efficiency of B and D
- B can complete the work in 36 days.
- D can complete the work in 25 days.

The efficiency of a worker is inversely proportional to the time taken to complete the work. Thus, we can express their efficiencies as follows:

- Efficiency of B (E_B) = 1/36 work/day
- Efficiency of D (E_D) = 1/25 work/day

To make calculations easier, we can convert these efficiencies to a common unit. Let's assume the total work is 3600 units (as calculated later).

- Efficiency of B = 3600/36 = 100 units/day
- Efficiency of D = 3600/25 = 144 units/day

Step 2: Calculate the efficiency of C
- C is 50% more efficient than B.

Thus, the efficiency of C (E_C) can be calculated as:
EC=EB+0.5×EB=1.5×EB=1.5×100=150 units/day

Step 3: Calculate the efficiency of A
- A is 20% less efficient than C.

Thus, the efficiency of A (E_A) can be calculated as:
EA=EC0.2×EC=0.8×EC=0.8×150=120 units/day

Step 4: Calculate the modified efficiencies of B and C
- B is working with 56% more efficiency than usual:
Modified efficiency of B=EB+0.56×EB=1.56×EB=1.56×100=156 units/day

- C is working with 20% more efficiency than usual:
Modified efficiency of C=EC+0.2×EC=1.2×EC=1.2×150=180 units/day

Step 5: Calculate the total efficiency when A, B, C, and D work together
Now, we can sum the efficiencies of A, B, C, and D:
Total Efficiency=EA+Modified efficiency of B+Modified efficiency of C+ED
=120+156+180+144=600 units/day

Step 6: Calculate the total work
We assumed the total work to be 3600 units.

Step 7: Calculate the time taken to complete the work
Using the formula:
Time=Total WorkTotal Efficiency
Time=3600600=6 days

Final Answer
The work will be completed in 6 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

    A10days
    B712 days
    C12days
    D1012 days
  • A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?

    A5 days
    B4 days
    C3 days
    D2 days
  • A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in:
    A किसी निश्चित कार्य को 40 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 22% अधिक कार्य कुशल है | वे 5 दिनों तक एक साथ कार्य करते हैं | शेष कार्य अकेले पूरा करने में B को कितने दिन लगेंगे ?

    A20(12) days
    B16(15) days
    C20(34) days
    D16(35) days