Efficiency of A is two times more than efficiency of B. Both A & B start working alternatively, starting with A and they complete the work in total 7423 days. C can alone complete the same work in 100 days.
If A, B & C work for 36 days, 18 days & 16 days and get total wage of Rs. 2500, then find difference between wage of share of B & C together and wage share of A?

A

900 Rs.

B

1500 Rs.

C

1100 Rs.

D

1800 Rs.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down as follows:

Step 1: Determine the Efficiency of A and B
Given that the efficiency of A is two times more than the efficiency of B, we can denote the efficiency of B as x. Therefore, the efficiency of A will be 2x.

Step 2: Calculate Total Work Done
A and B work alternately, starting with A, and they complete the work in 7423 days. We convert this mixed fraction into an improper fraction:
7423=2243 days

In two days, A and B together complete:
Work done in 2 days=A's work+B's work=2x+x=3x

The number of complete 2-day cycles in 2243 days is:
Number of cycles=224/32=1123

Thus, the total work done in these cycles is:
Total work=(1123)×3x=112x

Step 3: Calculate Total Work in Terms of Days
Now, we need to account for the extra day (since 2243 is not a whole number). The extra work done by A on the last day is:
Extra work by A=2x

So, the total work W is:
W=112x+2x=114x

Step 4: Relate Work to C's Efficiency
C can complete the same work in 100 days, so C's efficiency is:
C's efficiency=W100=114x100=1.14x

Step 5: Calculate Work Done by A, B, and C
Now we calculate the work done by A, B, and C over the given days:
- A works for 36 days:
Work by A=36×2x=72x
- B works for 18 days:
Work by B=18×x=18x
- C works for 16 days:
Work by C=16×1.14x=18.24x

Step 6: Total Work Done
Adding the work done by A, B, and C:
Total work done=72x+18x+18.24x=108.24x

Step 7: Verify Total Work
Since we calculated earlier that the total work W=114x, we can see that:
108.24x<114x
This indicates that the total work is indeed consistent with the original work calculation.

Step 8: Calculate Wages
The total wage for the work done is Rs. 2500. The share of wages is proportional to the work done:
- Total work done by A, B, and C:
Total work=114x

- Wage per unit work:
Wage per unit=2500114x

Step 9: Calculate Individual Wages
- Wage of A:
Wage of A=72x×2500114x=72×2500114=1263.16
- Wage of B:
Wage of B=18x×2500114x=18×2500114=394.74
- Wage of C:
Wage of C=18.24x×2500114x=18.24×2500114=400.00

Step 10: Calculate the Difference in Wages
Now, we find the difference between the combined wage of B and C and the wage of A:
Combined wage of B and C=394.74+400.00=794.74
Difference=1263.16794.74=468.42

Conclusion
The difference between the wage share of B and C together and the wage share of A is approximately Rs. 468.42.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Efficiency of Q is two times more than efficiency of P. Both
    started working alternatively, starting with Q and completed
    the work in total 35 days. If R alone complete the same work in
    48 days then find in how many days P and R together will
    complete the work?

    A24 days
    B28 days
    C36 days
    D27 days
  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42