P and Q together can complete a work in 24 days, while Q and R working together can complete the same job in 32 days. P and Q started the work and did it for 8 days, after that P left the work and R joined Q and after 12 more days, Q also left the work. Then, the remaining work was completed by R in 28 days. Find in how many days R will complete the work alone?
96 days
72 days
108 days
90 days
The correct Answer is:A
To solve the problem step by step, we will break down the information provided and calculate the required values systematically.
Step 1: Calculate Total Work
P and Q together can complete the work in 24 days. Therefore, their combined efficiency is:
Efficiency of P + Q=124 work/day
Similarly, Q and R can complete the work in 32 days, so their combined efficiency is:
Efficiency of Q + R=132 work/day
To find the total work, we can use the least common multiple (LCM) of the two time periods:
Total Work=LCM(24,32)=96 units of work
Step 2: Calculate Individual Efficiencies
From the efficiencies calculated:
- Let the efficiency of P be p, Q be q, and R be r.
- We have:
p+q=9624=4 (units of work/day)
q+r=9632=3 (units of work/day)
Step 3: Set Up Equations
Now, we can set up the equations:
1. p+q=4
2. q+r=3
From the first equation, we can express p in terms of q:
p=4−q
Substituting p into the second equation:
(4−q)+r=3
This simplifies to:
r=3−4+q=q−1
Step 4: Calculate Work Done by P and Q
P and Q work together for 8 days:
Work done by P + Q in 8 days=8×4=32 units
Step 5: Calculate Remaining Work
The total work is 96 units, so the remaining work after P and Q have worked for 8 days is:
Remaining Work=96−32=64 units
Step 6: Calculate Work Done by Q and R
Next, Q and R work together for 12 days:
Work done by Q + R in 12 days=12×3=36 units
Step 7: Calculate Remaining Work After Q and R
After Q and R have worked for 12 days, the remaining work is:
Remaining Work=64−36=28 units
Step 8: Calculate Work Done by R
R completes the remaining 28 units of work in 28 days:
Efficiency of R=28 units28 days=1 unit of work/day
Step 9: Calculate Time Taken by R Alone
To find out how many days R will take to complete the entire work alone:
Time taken by R=Total WorkEfficiency of R=961=96 days
Final Answer
R will complete the work alone in 96 days.
P and Q together can complete the work in 24 days. Therefore, their combined efficiency is:
Efficiency of P + Q=124 work/day
Similarly, Q and R can complete the work in 32 days, so their combined efficiency is:
Efficiency of Q + R=132 work/day
Total Work=LCM(24,32)=96 units of work
From the efficiencies calculated:
- Let the efficiency of P be p, Q be q, and R be r.
- We have:
p+q=9624=4 (units of work/day)
q+r=9632=3 (units of work/day)
Now, we can set up the equations:
1. p+q=4
2. q+r=3
p=4−q
(4−q)+r=3
This simplifies to:
r=3−4+q=q−1
P and Q work together for 8 days:
Work done by P + Q in 8 days=8×4=32 units
The total work is 96 units, so the remaining work after P and Q have worked for 8 days is:
Remaining Work=96−32=64 units
Next, Q and R work together for 12 days:
Work done by Q + R in 12 days=12×3=36 units
After Q and R have worked for 12 days, the remaining work is:
Remaining Work=64−36=28 units
R completes the remaining 28 units of work in 28 days:
Efficiency of R=28 units28 days=1 unit of work/day
To find out how many days R will take to complete the entire work alone:
Time taken by R=Total WorkEfficiency of R=961=96 days
R will complete the work alone in 96 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View Solution
Knowledge Check
P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A40B72C84D90P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A1800B900C1200D1500P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
A48 daysB42 daysC45 daysD51 days
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View SolutionA and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View SolutionA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View Solution