Anu can complete a work in 10 days. Manu is 25% more efficient than Annu and Sonu is 60% more efficient then Manu. Working together, how long would they take to finish the job?

A

358 days

B

567 days

C

2617 days

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will calculate the efficiencies of Anu, Manu, and Sonu, and then determine how long they will take to complete the work together.

Step 1: Determine Anu's Work Rate
Anu can complete the work in 10 days. Therefore, her work rate is:
Work rate of Anu=1 work10 days=0.1 work per day

Step 2: Calculate Manu's Work Rate
Manu is 25% more efficient than Anu. To find Manu's efficiency:
Efficiency of Manu=Efficiency of Anu×(1+0.25)=0.1×1.25=0.125 work per day

Step 3: Calculate Sonu's Work Rate
Sonu is 60% more efficient than Manu. Therefore, Sonu's efficiency is:
Efficiency of Sonu=Efficiency of Manu×(1+0.60)=0.125×1.6=0.2 work per day

Step 4: Calculate Total Work Rate When Working Together
Now, we can find the total work rate when Anu, Manu, and Sonu work together:
Total efficiency=Efficiency of Anu+Efficiency of Manu+Efficiency of Sonu
Total efficiency=0.1+0.125+0.2=0.425 work per day

Step 5: Calculate Time to Complete the Work
Assuming the total work is 1 unit, the time taken to complete the work when they work together is:
Time=Total workTotal efficiency=1 work0.425 work per day2.3529 days

To express this in a more understandable format:
Time2 days and 0.3529 days
Converting 0.3529 days into hours (1 day = 24 hours):
0.3529×248.47 hours

Final Answer
Thus, Anu, Manu, and Sonu together will take approximately 2 days and 8.47 hours to finish the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

    A10days
    B712 days
    C12days
    D1012 days
  • Question 2 - Select One

    A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in:
    A किसी निश्चित कार्य को 40 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 22% अधिक कार्य कुशल है | वे 5 दिनों तक एक साथ कार्य करते हैं | शेष कार्य अकेले पूरा करने में B को कितने दिन लगेंगे ?

    A20(12) days
    B16(15) days
    C20(34) days
    D16(35) days
  • Question 3 - Select One

    A can do a picec of work in 10 days and B is 25% more
    efficient than A. In what time will the work be finished if A
    and B work together ?

    A449 days
    B557 days
    C5 days
    D623 days