Anu can complete a work in 10 days. Manu is 25% more efficient than Annu and Sonu is 60% more efficient then Manu. Working together, how long would they take to finish the job?
358 days
567 days
2617 days
None of these
The correct Answer is:C
To solve the problem step by step, we will calculate the efficiencies of Anu, Manu, and Sonu, and then determine how long they will take to complete the work together.
Step 1: Determine Anu's Work Rate
Anu can complete the work in 10 days. Therefore, her work rate is:
Work rate of Anu=1 work10 days=0.1 work per day
Step 2: Calculate Manu's Work Rate
Manu is 25% more efficient than Anu. To find Manu's efficiency:
Efficiency of Manu=Efficiency of Anu×(1+0.25)=0.1×1.25=0.125 work per day
Step 3: Calculate Sonu's Work Rate
Sonu is 60% more efficient than Manu. Therefore, Sonu's efficiency is:
Efficiency of Sonu=Efficiency of Manu×(1+0.60)=0.125×1.6=0.2 work per day
Step 4: Calculate Total Work Rate When Working Together
Now, we can find the total work rate when Anu, Manu, and Sonu work together:
Total efficiency=Efficiency of Anu+Efficiency of Manu+Efficiency of Sonu
Total efficiency=0.1+0.125+0.2=0.425 work per day
Step 5: Calculate Time to Complete the Work
Assuming the total work is 1 unit, the time taken to complete the work when they work together is:
Time=Total workTotal efficiency=1 work0.425 work per day≈2.3529 days
To express this in a more understandable format:
Time≈2 days and 0.3529 days
Converting 0.3529 days into hours (1 day = 24 hours):
0.3529×24≈8.47 hours
Final Answer
Thus, Anu, Manu, and Sonu together will take approximately 2 days and 8.47 hours to finish the work.
---
Anu can complete the work in 10 days. Therefore, her work rate is:
Work rate of Anu=1 work10 days=0.1 work per day
Manu is 25% more efficient than Anu. To find Manu's efficiency:
Efficiency of Manu=Efficiency of Anu×(1+0.25)=0.1×1.25=0.125 work per day
Sonu is 60% more efficient than Manu. Therefore, Sonu's efficiency is:
Efficiency of Sonu=Efficiency of Manu×(1+0.60)=0.125×1.6=0.2 work per day
Now, we can find the total work rate when Anu, Manu, and Sonu work together:
Total efficiency=Efficiency of Anu+Efficiency of Manu+Efficiency of Sonu
Total efficiency=0.1+0.125+0.2=0.425 work per day
Assuming the total work is 1 unit, the time taken to complete the work when they work together is:
Time=Total workTotal efficiency=1 work0.425 work per day≈2.3529 days
Time≈2 days and 0.3529 days
Converting 0.3529 days into hours (1 day = 24 hours):
0.3529×24≈8.47 hours
Thus, Anu, Manu, and Sonu together will take approximately 2 days and 8.47 hours to finish the work.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 days - Question 2 - Select One
A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in:
A किसी निश्चित कार्य को 40 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 22% अधिक कार्य कुशल है | वे 5 दिनों तक एक साथ कार्य करते हैं | शेष कार्य अकेले पूरा करने में B को कितने दिन लगेंगे ?A20(12) daysB16(15) daysC20(34) daysD16(35) days - Question 3 - Select One
A can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?A449 daysB557 daysC5 daysD623 days
To complete a certain task, X is 40% more efficient than Y, and Z is 40% less efficient than Y. Working together, they can complete the task in 21 days. Y and Z together worked for 35 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को पूरा करने के लिए, X, Y की तुलना में 40% अधिक कार्य कुशल है तथा Z, Y से 40% कम कार्य कुशल है| एक साथ कार्य करते हुए, वे इस कार्य को 21 दिनों में पूरा कर सकते हैं | Y तथा Z ने 35 दिनों तक एक साथ कार्य किया | शेष कार्य A अकेला कितने दिनों में पूरा करेगा ?View SolutionP can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionA can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View Solution